Metal Flashing Details

10.2.1.2.jpg

FABRICATION PROCEDURE

(1) Metal Cap Flashing: Cut to form a 25mm (1") wide flange for seam fabrication at cap flashing /wall transitions. Fasten outside face with continuous concealed clip-type fasteners or with two concealed discontinuous clips or cladding screws evenly spaced between seams. See SBS Roof Systems - 12.6 Cap Flashings, Base Flashings and Reglets (parallel Standards are shown for all Low Slope Roof Systems) for additional reqiurements for metal flashings. Cap flashing over 100 mm (4") in width must provide positive slope to roof area.

(2) Gusset Flange: Site fabricated a minimum of 100mm (4") wider than the top, inside and outside face of metal cap flashing. Metal gusset flange to match profile of cap flashing with an additional allowance of 12.7 mm (1/2") of material for seaming. Gusset Flange must lap under sheathing membrane and wall cladding or finish by a minimum of 75mm (3").

(3) Double Fold Seam: Site formed standing seam folded flat on back surface of wall transition gusset to form double fold seam. Optional: Install polyurethane caulking seam tape prior to forming double folded seam.

NOTE

NOTE: Refer to RoofStar Guarantee Standards for additional requirements.