SBS Flanged Insert Drain (Clamping Ring)

Jump to: navigation, search

SBS Flanged Insert Drain (Clamping Ring)



Division D - Construction Details


SBS | Flanged Insert Drain (Clamping Ring) ( Article 11.3.3.6.)

Notice to Reader
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).

The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text.

SBS Details

D1.7.8-3.jpg


1 WORK INCLUDED

(1) Supporting Deck Overlay
Required when insulation is too thin to span flutes of steel decking or when required as thermal barrier by design authority.
(2) Air or Vapour Control Layers
If required by design authority.
(3) Insulation
Mechanically fastened. See available insulation products in the Accepted Materials Division of this Manual.
(4) Insulation Overlay
Asphalt adhered or mechanically fastened. Two layers required over heat-sensitive insulation.
(5) Field Base Membrane
Adhered to overlay board using asphalt, cold adhesive, self-adhered, mechanical attachment or torch applied according to manufacturer's specification and to RoofStar Guarantee Standards. Torching directly to wood surfaces is not permitted.
(6) Mastic
Compatible mastic accepted by the membrane manufacturer.
(7) Base Membrane Flashing
Adhered according to manufacturer's specifications and to RoofStar Guarantee Standards.
(8) Field Cap Membrane
Applied according to manufacturer's printed instructions and to RoofStar Guarantee Standards.

2 RELATED WORK BY OTHERS

(A) Acceptable Supporting Deck Structure
(B) Clamping Copper Drain
Primed and mechanically fastened. Installed in bed of compatible mastic.
  • Leader size is determined by design authority using the calculation found in the BC Building Code at Appendix P.7.4.10 and Section 7.4.10.11 (Section 7.4.10.10 for gutters) in conjunction with the 15 minute rainfall value from the National Building Code, Appendix C.

NOTE: See the Standard for additional requirements.