SBS Fire Separation Joint

Jump to: navigation, search

SBS Fire Separation Joint

Revision as of 16:24, 20 August 2019 by James Klassen (talk | contribs) (RELATED WORK BY OTHERS)
RoofStar Guarantee Standards are blue-linked
SBS Details

10.3.4.3.jpg

1 WORK INCLUDED

(1) Supporting Deck Overlay
If required by design authority.
(2) Air or Vapour Control Layers
If required by design authority.
(3) Insulation
See available insulation products in the Accepted Materials section of this Manual.
(4) Insulation Overlay
Where required.
(5) Primary Membrane and Membrane Protection
(6) Membrane Flashing
(7) Membrane Counter Flashing
(8) Base Metal Flashing
Mechanically fasten to top of plywood backing. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
(9) Metal Flashing / Cladding
(10) Secondary Metal Cap Flashing
Joints to be offset from Cap Flashing, OR Water Channeling Clip may be used (See inset in detail D1.7.19 Roof-Wall Transitions (Fire Separation Wall)), OR solder standing seam joints. Do NOT place combustible materials over top of firewall.
(11) Metal Cap Flashing
Standing seam joints required.

2 RELATED WORK BY OTHERS

(A) Acceptable Supporting Deck Structure
(B) Acceptable Wall Surface
(C) Wood Blocking
(D) Grouted Finish
Sloped surface to promote drainage off cap flashing.

NOTE: Refer to RoofStar Guarantee Standards for additional requirements.




Back to RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies

Back to SBS Modified Bitumen Construction Details

Back to Construction Details