SBS Flanged Insert Drain

Jump to: navigation, search

SBS Flanged Insert Drain

Revision as of 16:13, 19 July 2016 by James Klassen (talk | contribs) (RELATED WORK BY OTHERS =)

10.3.6.2.jpg

1 WORK INCLUDED

(1) Gypsum Overlay Board: If required by design authority.

(2) Vapour Retarder: If required by design authority.

(3) Insulation: See list of accepted materials in Section 2.2.

(4) Insulation Overlay: Where required. See RGC Guarantee Standard B4.1, B4.2 and C4.1

(5) Primary Membrane and Membrane Protection

(6) Mastic: As approved by manufacturer.

(7) Membrane Flashing: Onto primed drain flange or adhesive for non-bituminous flexible membrane systems.

2 RELATED WORK BY OTHERS =

(A) Acceptable Deck

(B) Roof Drain Assembly


NOTE
  • Refer to RGC Guarantee Standards for additional requirements
  • Leader size is determined by using the calculation found in the BC Building Code at Appendix P.7.4.10 and Section 7.4.10.11 (Section 7.4.10.10 for gutters) in conjunction with the 15-minute rainfall value from the National Building Code, Appendix C.


Refer to RGC Guarantee Standards for additional requirements.





Back to SBS Application

Back to SBS Construction Details

Back to Construction Details