Difference between revisions of "TS Details:E4.7.1 (Tile - Hips & Ridges)"

Jump to: navigation, search

Difference between revisions of "TS Details:E4.7.1 (Tile - Hips & Ridges)"

Line 3: Line 3:
 
Tiles are started at the low end of hips or the leeward end of ridges. Each tile is nailed through the hole provided into the nailer. The lap of the next tile covers the nail. The last ridge tile nails will have to be caulked.
 
Tiles are started at the low end of hips or the leeward end of ridges. Each tile is nailed through the hole provided into the nailer. The lap of the next tile covers the nail. The last ridge tile nails will have to be caulked.
  
 +
{| class="wikitable" | style="color: black; background-color: orange; width: 100%;text-align:center"
 +
| colspan="2"  | <big>'''''RoofStar Guarantee Standards''''' are <span style="color:#6495ed">'''blue-linked'''</span></big>
 +
|}
 
<div class="panel panel-success">
 
<div class="panel panel-success">
 
<div class="panel-heading"><big>'''Tile Roofing Details'''</big></div>
 
<div class="panel-heading"><big>'''Tile Roofing Details'''</big></div>

Revision as of 15:14, 1 September 2016

Ridge and hip tiles are applied after the field tiles are terminated against the nailer board. A sealant, mortar or plaster cement should be applied to the tops of the field tile and between laps of the ridge / hip tile. This prevents entry of wind driven rain or snow.

Tiles are started at the low end of hips or the leeward end of ridges. Each tile is nailed through the hole provided into the nailer. The lap of the next tile covers the nail. The last ridge tile nails will have to be caulked.

RoofStar Guarantee Standards are blue-linked
Tile Roofing Details

7.3.2.2.12.jpg

7.3.2.2.13.jpg




Back to Slate Application

Back to Tile and Slate Construction Details

Back to Construction Details