Difference between revisions of "SBS 11.3.2.2-1 Cast Iron Drains"
Difference between revisions of "SBS 11.3.2.2-1 Cast Iron Drains"
(→RELATED WORK BY OTHERS) |
(→RELATED WORK BY OTHERS) |
||
Line 37: | Line 37: | ||
− | [[RoofStar Guarantee Standards for SBS Roof | + | [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies |<i class="fa fa-chevron-circle-left fa" ></i> Back to ''RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies'']] |
− | [[SBS Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''SBS Construction Details'']] | + | [[SBS Modified Bitumen Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''SBS Modified Bitumen Construction Details'']] |
[[Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''Construction Details'']] | [[Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''Construction Details'']] |
Revision as of 14:54, 27 September 2017
RoofStar Guarantee Standards are blue-linked |
SBS Details
1 WORK INCLUDED
- (1) Gypsum Deck Overlay
- If required by design authority.
- (2) Vapour Retarder
- If required by design authority.
- (3) Insulation
- Mechanically fastened. See available insulation products in the Accepted Materials section of this Manual.
- (4) Insulation Overlay Board
- Asphalt adhered or mechanically fastened. Two layers required over heat-sensitive insulation.
- (5) Primary Membrane and Membrane Protection
- (6) Mastic
- As approved by manufacturer.
- (7) Base Sheet Flashing
- As approved by membrane manufacturer (See (C) below).
2 RELATED WORK BY OTHERS
- (A) Acceptable Deck
- (B) Roof Drain Assembly
- (C) Lead Flashing
- Minimum 15 kg / m² (3 lb / ft²) weight lead sheet; flange extending minimum 25 mm (1") into bowl to 150 mm (6") beyond perimeter of drain; embed in mastic (6) and prime top surface where required by manufacturer or minimum 1 m x 1 m (39" x 39") 3 mm thick modified bituminous base sheet; to be supplied by trade supplying roof drain. For asphalt and gravel built-up systems only.
NOTE: Refer to RoofStar Guarantee Standards for additional requirements.
- Leader size is determined by using the calculation found in the BC Building Code at Appendix P.7.4.10 and Section 7.4.10.11 (Section 7.4.10.10 for gutters)(current edition) in conjunction with the 15-minute rainfall value from the National Building Code, Appendix C.
Back to RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies