Difference between revisions of "SBS Low Door Opening"

Jump to: navigation, search

Difference between revisions of "SBS Low Door Opening"

(RELATED WORK BY OTHERS)
Line 13: Line 13:
 
<div class="col-md-6">
 
<div class="col-md-6">
 
=== WORK INCLUDED ===
 
=== WORK INCLUDED ===
;(1) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSBASE|'''Primary Roof Membrane''']]
+
;(1) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSBASE|'''Primary Roof Membrane''']]
;(2) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSDOOR|'''Membrane Flashing''']]: Carried up wall minimum 200 mm (8") above roof surface. At doorsill openings membrane flashing may be less than 200mm (8") in height but must not be less than 100mm (4") in height above the primary roof membrane. When doorsills are less than 200mm (8") a metal waterstop flashing must be mechanically attached to backside of doorsill framing or opening and be sealed with membrane flashing. Membrane gussets must be installed at doorsill opening corners.
+
;(2) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSDOOR|'''Membrane Flashing''']]: Carried up wall minimum 200 mm (8") above roof surface. At door sill openings membrane flashing may be less than 200mm (8") in height but must not be less than 100mm (4") in height above the primary roof membrane. When door sills are less than 200mm (8") a metal waterstop flashing must be mechanically attached to backside of door sill framing or opening and be sealed with membrane flashing. Membrane gussets must be installed at door sill opening corners.
 
;(3) '''Protection/Drainage Layer''': Optional
 
;(3) '''Protection/Drainage Layer''': Optional
;(4) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Metal Base Flashing''']]: Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
+
;(4) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#METALCAP-SBS|'''Metal Base Flashing''']]: Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
;(5) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Metal Counter-flashing''']]
+
;(5) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#METALCAP-SBS|'''Metal Counter-flashing''']]
;(6) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSDOOR|'''Metal Water-stop Flashing''']]: Mechanically attached to inside of door sill framing or opening. Cut flashing to fit opening and install membrane gussets at corners.
+
;(6) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSDOOR|'''Metal Water-stop Flashing''']]: Mechanically attached to inside of door sill framing or opening. Cut flashing to fit opening and install membrane gussets at corners.
;(7) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSDOOR|'''Metal Pan Sill Flashing''']]: Optional - Metal pan with water stop formed with pan folded, welded or soldered corners mechanically attached to inside of door sill frame or opening and sealed with membrane flashing.
+
;(7) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSDOOR|'''Metal Pan Sill Flashing''']]: Optional - Metal pan with water stop formed with pan folded, welded or soldered corners mechanically attached to inside of door sill frame or opening and sealed with membrane flashing.
  
 
<hr>
 
<hr>
  
 
=== RELATED WORK BY OTHERS ===
 
=== RELATED WORK BY OTHERS ===
;(A) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSDECKS|'''Acceptable Deck''']]: Concrete slab shown  
+
;(A) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSDECKS|'''Acceptable Deck''']]: Concrete slab shown  
 
;(B) '''Wall Cladding and Flashing'''
 
;(B) '''Wall Cladding and Flashing'''
 
</div><!-- COL-6-MD -->
 
</div><!-- COL-6-MD -->

Revision as of 16:09, 23 October 2017

RoofStar Guarantee Standards are blue-linked
SBS Details

1 WORK INCLUDED

(1) Primary Roof Membrane
(2) Membrane Flashing
Carried up wall minimum 200 mm (8") above roof surface. At door sill openings membrane flashing may be less than 200mm (8") in height but must not be less than 100mm (4") in height above the primary roof membrane. When door sills are less than 200mm (8") a metal waterstop flashing must be mechanically attached to backside of door sill framing or opening and be sealed with membrane flashing. Membrane gussets must be installed at door sill opening corners.
(3) Protection/Drainage Layer
Optional
(4) Metal Base Flashing
Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
(5) Metal Counter-flashing
(6) Metal Water-stop Flashing
Mechanically attached to inside of door sill framing or opening. Cut flashing to fit opening and install membrane gussets at corners.
(7) Metal Pan Sill Flashing
Optional - Metal pan with water stop formed with pan folded, welded or soldered corners mechanically attached to inside of door sill frame or opening and sealed with membrane flashing.

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
Concrete slab shown
(B) Wall Cladding and Flashing

NOTE: Refer to RoofStar Guarantee Standards for additional requirements.