Difference between revisions of "SBS Parapet-Wall Connection"
Difference between revisions of "SBS Parapet-Wall Connection"
(→WORK INCLUDED) |
(→WORK INCLUDED) |
||
Line 29: | Line 29: | ||
:As required. | :As required. | ||
;(5) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSBASE|'''Primary Membrane''']] and [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSPROTECTION| '''Membrane Protection''']]: | ;(5) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSBASE|'''Primary Membrane''']] and [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSPROTECTION| '''Membrane Protection''']]: | ||
− | ;(6) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies# | + | ;(6) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBS-STRIPPING|'''Membrane Flashing (attachment & termination)''']]: Mechanically fasten at terminations. At least one ply must extend over outside edge. |
;(7) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#METALCAP-SBS|'''Metal Base Flashing''']]: Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats. | ;(7) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#METALCAP-SBS|'''Metal Base Flashing''']]: Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats. | ||
;(8) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#METALCAP-SBS|'''Metal Cap Flashing''']]: Must overlap exterior wall finish. Fasten with concealed clip-type fasteners <b>or</b> cladding screws evenly spaced between seams. | ;(8) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#METALCAP-SBS|'''Metal Cap Flashing''']]: Must overlap exterior wall finish. Fasten with concealed clip-type fasteners <b>or</b> cladding screws evenly spaced between seams. |
Revision as of 19:05, 29 January 2019
RoofStar Guarantee Standards are blue-linked |
SBS Details
1 WORK INCLUDED
- (1) Supporting Deck Overlay
- If required by design authority.
- (2) Air or Vapour Control Layers
- If required by design authority.
- (3) Insulation
- See list of Accepted Materials.
- (4) Insulation Overlay
- As required.
- (5) Primary Membrane and Membrane Protection
- (6) Membrane Flashing (attachment & termination)
- Mechanically fasten at terminations. At least one ply must extend over outside edge.
- (7) Metal Base Flashing
- Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
- (8) Metal Cap Flashing
- Must overlap exterior wall finish. Fasten with concealed clip-type fasteners or cladding screws evenly spaced between seams.
- (9) Wall Tie-in
- Minimum 2 mm (0.078") self-adhered modified bitumen or flexible membrane manufacturers approved detail.
- (10) Metal Counter-flashing
2 RELATED WORK BY OTHERS
- (A) Acceptable Supporting Deck Structure
- (B) Air and Vapour Control Layer Seal
- (C) Acceptable Wall Surface
- (D) Wood Blocking
- (E) Sloped Wood Blocking
- Required over 100 mm (4") parapet width.
- (F) Wall Sheathing Membrane
- Minimum 1 mm (0.040") self-adhered modified bitumen.
- (G) Wall Cladding
NOTE: Refer to RoofStar Guarantee Standards for additional requirements.
Back to RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies