'''NOTE''': Refer to '''''RoofStar Guarantee Standards''''' for additional requirements.
 
'''NOTE''': Refer to '''''RoofStar Guarantee Standards''''' for additional requirements.
 
*<b>WARNING: <u>DO NOT USE</u> THIS DETAIL WITH HOT PIPES.</b>
 
*<b>WARNING: <u>DO NOT USE</u> THIS DETAIL WITH HOT PIPES.</b>
*<b>AVOID THIS DETAIL:</b> Wherever possible use Flanged Metal Stack Flashing or Curbed Opening (See Section 10.3).
+
*<b>AVOID THIS DETAIL:</b> Wherever possible use Flanged Metal Stack Flashing or Curbed Opening (See '''11.1.2.2 Curbs and Penetrations''').
  
  

Revision as of 19:03, 30 January 2019

RoofStar Guarantee Standards are blue-linked
SBS Details

10.3.5.4.jpg

1 WORK INCLUDED

(1) Supporting Deck Overlay
If required by design authority.
(2) Air or Vapour Control Layers
If required by design authority
(3) Insulation
Mechanically fastened. See available insulation products in the Accepted Materials section of this Manual.
(4) Insulation Overlay
As required.
(5) Primary Membrane and Membrane Protection
(6) Compatible Mastic
Use only the membrane manufacturer's approved sealant.
(7) Sealant Pocket
Minimum 100 mm (4") flange onto roof membrane. All corners, with the exception of one job-site formed double standing seam corner joint and adjoining lapped flange joining, shall be closed and soldered. Minimum height of gum pan to be 100 mm (4").
(8) Membrane Flashing
Onto primed metal flashing flange.
(9) Packing
To prevent displacement of compatible mastic.
(10) Structural Sealant
Use only the membrane manufacturers’ approved proprietary polyurethane based structural sealant.
(11) Back-up Storm Collar
To be installed whenever practical. Caulk at top of collar.

2 RELATED WORK BY OTHERS

(A) Acceptable Supporting Deck Structure
(B) Protrusion
(C) Wood Blocking]]

NOTE: Refer to RoofStar Guarantee Standards for additional requirements.

  • WARNING: DO NOT USE THIS DETAIL WITH HOT PIPES.
  • AVOID THIS DETAIL: Wherever possible use Flanged Metal Stack Flashing or Curbed Opening (See 11.1.2.2 Curbs and Penetrations).




Back to RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies

Back to SBS Modified Bitumen Construction Details

Back to Construction Details