Difference between revisions of "SBS Open-wall Scupper Drain"
Difference between revisions of "SBS Open-wall Scupper Drain"
Line 13: | Line 13: | ||
<div class="col-md-6"> | <div class="col-md-6"> | ||
=== WORK INCLUDED === | === WORK INCLUDED === | ||
− | ;(1) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies# | + | ;(1) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSAIRVAPOUR|'''Air or Vapour Control Layers''']]: If required by design authority. |
;(2) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATION|'''Insulation''']]: Mechanically fastened. See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual. | ;(2) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATION|'''Insulation''']]: Mechanically fastened. See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual. | ||
− | ;(3) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATIONOVERLAY|'''Insulation Overlay | + | ;(3) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATIONOVERLAY|'''Insulation Overlay''']]: Where required. |
− | ;(4) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSBASE|'''Primary Membrane and Membrane Protection''']] | + | ;(4) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSBASE|'''Primary Membrane''']] and [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSPROTECTION| '''Membrane Protection''']] |
;(5) '''Metal Scupper with Hopper''': The outside face of scupper to be 37.7mm (1½") <b><u>lower</u></b><u> </u>than the box height with a 12.7mm (½") drip edge. Installed in a thin bed of compatible mastic. Interface between outside wall and scupper should be caulked with appropriate sealant. Installed when wall finish is complete prior to completion of roofing or sheet metal (e.g.: re-roofing). | ;(5) '''Metal Scupper with Hopper''': The outside face of scupper to be 37.7mm (1½") <b><u>lower</u></b><u> </u>than the box height with a 12.7mm (½") drip edge. Installed in a thin bed of compatible mastic. Interface between outside wall and scupper should be caulked with appropriate sealant. Installed when wall finish is complete prior to completion of roofing or sheet metal (e.g.: re-roofing). | ||
;(6) '''Scupper Membrane Flashing''' | ;(6) '''Scupper Membrane Flashing''' | ||
Line 26: | Line 26: | ||
=== RELATED WORK BY OTHERS === | === RELATED WORK BY OTHERS === | ||
− | ;(A) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSDECKS|'''Acceptable Deck''']] | + | ;(A) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSDECKS|'''Acceptable Supporting Deck Structure''']] |
;(B) '''Air / Vapour Seal''' | ;(B) '''Air / Vapour Seal''' | ||
− | ;(C) | + | ;(C) '''Wood Blocking''' |
;(D) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSWALLSUB|'''Acceptable Wall Surface - Plywood''']] | ;(D) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSWALLSUB|'''Acceptable Wall Surface - Plywood''']] | ||
;(E) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSWALLSUB|'''Wall Finish''']]: Interface between outside wall and scupper to be caulked with appropriate sealant. Installed by trade responsible for outside wall finish if roofing and metal flashing has been completed prior to exterior wall finish. | ;(E) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSWALLSUB|'''Wall Finish''']]: Interface between outside wall and scupper to be caulked with appropriate sealant. Installed by trade responsible for outside wall finish if roofing and metal flashing has been completed prior to exterior wall finish. |
Revision as of 19:29, 30 January 2019
RoofStar Guarantee Standards are blue-linked |
SBS Details
1 WORK INCLUDED
- (1) Air or Vapour Control Layers
- If required by design authority.
- (2) Insulation
- Mechanically fastened. See available insulation products in the Accepted Materials section of this Manual.
- (3) Insulation Overlay
- Where required.
- (4) Primary Membrane and Membrane Protection
- (5) Metal Scupper with Hopper
- The outside face of scupper to be 37.7mm (1½") lower than the box height with a 12.7mm (½") drip edge. Installed in a thin bed of compatible mastic. Interface between outside wall and scupper should be caulked with appropriate sealant. Installed when wall finish is complete prior to completion of roofing or sheet metal (e.g.: re-roofing).
- (6) Scupper Membrane Flashing
- (7) Membrane Flashing
- (8) Base Metal Flashing
- Mechanically fastened. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
- (9) Metal Cap Flashing
- Fasten with continuous concealed clip-type fasteners or cladding screws evenly spaced between seams. Flashing 8 and 9 may be one piece.
2 RELATED WORK BY OTHERS
- (A) Acceptable Supporting Deck Structure
- (B) Air / Vapour Seal
- (C) Wood Blocking
- (D) Acceptable Wall Surface - Plywood
- (E) Wall Finish
- Interface between outside wall and scupper to be caulked with appropriate sealant. Installed by trade responsible for outside wall finish if roofing and metal flashing has been completed prior to exterior wall finish.
NOTE: Refer to RoofStar Guarantee Standards for additional requirements.
Back to RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies