Difference between revisions of "EPDM Protected Roof Assembly (Typical)"
Difference between revisions of "EPDM Protected Roof Assembly (Typical)"
(→WORK INCLUDED) |
(→RELATED WORK BY OTHERS) |
||
Line 30: | Line 30: | ||
;(A) [[RoofStar Guarantee Standards for EPDM Membrane Systems#EPDMDECKS|'''Acceptable Deck''']] | ;(A) [[RoofStar Guarantee Standards for EPDM Membrane Systems#EPDMDECKS|'''Acceptable Deck''']] | ||
− | ;(B) | + | ;(B) Acceptable Parapet Surface: Surface must be smooth, dry and clean. Rough surface must be covered with treated plywood, to be determined by design authority or inspector or as required by manufacturer. |
− | ;(C) | + | ;(C) Sloped Wood Blocking: |
</div><!-- COL-6-MD --> | </div><!-- COL-6-MD --> | ||
</div><!-- PANEL BODY --> | </div><!-- PANEL BODY --> |
Revision as of 20:04, 18 February 2020
RoofStar Guarantee Standards are blue-linked |
EPDM Details
1 WORK INCLUDED
- (1) Protection Mat
- Provide protection between concrete deck and membrane with installation of manufacturer specified and RGC accepted protection mat or deck overlay boards.
- (2) Single-ply Membrane
- Installed according to manufacturer's instructions and RoofStar Guarantee Standards.
- (3) Adhesive
- Proprietary, installed according to manufacturer's instructions, usually brushed, rolled or sprayed.
- (4) Membrane Lap
- EPDM (thermoset) membrane may be joined using uncured tape or proprietary adhesive.
- (5) Fasteners
- Install according to manufacturer's instructions (style may vary depending on material type and manufacturer's specification). May vary from drawing.
- (6) Membrane Flashing
- Adhered according to manufacturer's printed specifications using proprietary adhesive. Must be carried to outside of parapet or minimum 200 mm (8") above finished roof surface. Adhered to primary membrane.
- (7) Insulation
- Mechanically attached. Installed according to RoofStar Guarantee Standards. See available insulation products in the Accepted Materials section of this Manual.
- (8) Filter Fabric
- Metal base flashing required.
- (9) Metal Flashing
- As required by RoofStar Guarantee Standards.
- (10) Ballast
- Gravel or concrete paving tiles.
- (11) Parapet Flashing
- As required by RoofStar Guarantee Standards.
2 RELATED WORK BY OTHERS
- (A) Acceptable Deck
- (B) Acceptable Parapet Surface
- Surface must be smooth, dry and clean. Rough surface must be covered with treated plywood, to be determined by design authority or inspector or as required by manufacturer.
- (C) Sloped Wood Blocking
NOTE: Refer to RoofStar Guarantee Standards for additional requirements.
RoofStar Guarantee Standards for EPDM Membrane Systems