Revision as of 14:51, 30 August 2021
Notice to Reader | |
Images used in a Construction Detail are representative and not prescriptive. Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the requirements of the Standard they represent. Unless otherwise required by the Standard, dimensions, the selection of materials and their application remains the responsibility of the Design Authority. The full text of the referenced requirements in the Standard may be read by using the blue hyperlinks |
SBS Details
1 WORK INCLUDED
- (1) Primer
- For self-adhered or torch-applied base membranes, as required by the membrane manufacturer.
- (2) Base Membrane (field)
- Torch-applied, adhered, self-adhered (as illustrated), or mechanically attached (subject to deck type and wind uplift design requirements). See Tables 9.1 and 9.2 for acceptable membrane types and securement options. See 9.3 for application requirements.
- (3) Mastic
- Applied beneath metal edge flashing. Refer to 10.3.5.2 (3)(2).
- (4) Metal Edge Flashing
- See 13.3.2 Fabrication for manufacturing requirements. See also 10.3.1.4 Low Roof Edges for application standards and securement. Hemmed edges are required; a kicked-out drip edge is optional but recommended (cf. 13.1.2.2 (10)).
- (5) Base Membrane (flashing)
- Applied to overlap metal flashing and the field base membrane.
- (6) Cap Membrane (field)
- Installed according to Part 9 standards and sealed along the exposed edge with an un-tooled bead of membrane compatible sealant (cf. 10.3.5.2 (3)(7)(2)).
2 RELATED WORK BY OTHERS
- (A) Acceptable Substrate
- Representative
- (B) Wall Assembly
- Representative
NOTE: See the Standard for additional requirements.
Back to SBS-modified Bitumen Membrane Roof System Details
© RCABC 2024
RoofStarTM is a registered Trademark of the RCABC.
No reproduction of this material, in whole or in part, is lawful without the expressed permission of the RCABC Guarantee Corp.