(WORK INCLUDED)
(WORK INCLUDED)
Line 25: Line 25:
  
 
;(1) [[SBS Roof Systems Standard#PART_5|'''Supporting Deck Overlay''']]: If required by design authority.
 
;(1) [[SBS Roof Systems Standard#PART_5|'''Supporting Deck Overlay''']]: If required by design authority.
;(2) [[SBS Roof Systems Standard#PART_6|'''Air or Vapour Control Layers''']]: <div data-tooltip="Updated 2021-Sep-01">If required by design authority.</div>
+
;(2) [[SBS Roof Systems Standard#PART_6|'''Air or Vapour Control Layers''']]: If required by design authority.<div data-tooltip="Updated 2021-Sep-01"></div>
 
;(3) [[SBS Roof Systems Standard#PART_7|'''Insulation''']]: See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual.
 
;(3) [[SBS Roof Systems Standard#PART_7|'''Insulation''']]: See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual.
 
;(4) [[SBS Roof Systems Standard#PART_8|'''Insulation Overlay''']]: As required.  
 
;(4) [[SBS Roof Systems Standard#PART_8|'''Insulation Overlay''']]: As required.  

Revision as of 17:16, 1 September 2021


Notice to Reader
Images used in a Construction Detail are representative and not prescriptive. Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the requirements of the Standard they represent. Unless otherwise required by the Standard, dimensions, the selection of materials and their application remains the responsibility of the Design Authority.

The full text of the referenced requirements in the Standard may be read by using the blue hyperlinks
SBS Details

10.3.1.3.jpg

Click below for a printable version of this page.
Print Sheet

1 WORK INCLUDED

(1) Supporting Deck Overlay
If required by design authority.
(2) Air or Vapour Control Layers
If required by design authority.
(3) Insulation
See available insulation products in the Accepted Materials section of this Manual.
(4) Insulation Overlay
As required.
(5) Primary Membrane and Membrane Protection
(6) Base Membrane Flashing
Mechanically fasten to parapet at termination.
(7) Base Metal Flashing
Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats. See Section 13.6 - Cap Flashings, Base Flashings and Reglets.
(8) Metal Counter Flashing
Minimum 25 mm (1") above roof surface.
(9) Metal Cap Flashing
Required whenever the primary roof membrane flashing/stripping is carried over the top of parapet walls. See Section 13.6 - Cap Flashings, Base Flashings and Reglets.

2 RELATED WORK BY OTHERS

(A) Acceptable Supporting Deck Structure
(B) Air / Vapour Seal
(C) Acceptable Wall Surface
(D) Wood Blocking
(E) Sloped Wood Blocking
Required over 100 mm (4") parapet width.
(F) Wall Sheathing Membrane
Minimum 1 mm (0.040") self-adhered modified bitumen.
(G) Exterior Wall Finish
(H) Metal Cap Flashing
Required by others whenever the primary roof membrane is not carried over top of the parapet and/or when the wall finish is by others. (Unless specified otherwise).
(I) Cap Flashing Underlay
Minimum 1 mm (0.040" or 40 mil) self-adhered modified bitumen.

NOTE: See the Standard for additional requirements.


Back to "SBS" Roof System Details