Difference between revisions of "SBS Flanged Insert Drain"
Difference between revisions of "SBS Flanged Insert Drain"
Line 17: | Line 17: | ||
<div class="col-md-6"> | <div class="col-md-6"> | ||
=== WORK INCLUDED === | === WORK INCLUDED === | ||
− | ;(1) [[SBS Roof Systems Standard# | + | ;(1) [[SBS Roof Systems Standard#PART_5|'''Supporting Deck Overlay''']]: If required by design authority. |
− | ;(2) [[SBS Roof Systems Standard# | + | ;(2) [[SBS Roof Systems Standard#PART_6|'''Air or Vapour Control Layers''']]: If required by design authority. |
− | ;(3) [[SBS Roof Systems Standard# | + | ;(3) [[SBS Roof Systems Standard#PART_7|'''Insulation''']]: See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual. |
− | ;(4) [[SBS Roof Systems Standard# | + | ;(4) [[SBS Roof Systems Standard#PART_8|'''Insulation Overlay''']]: Where required. |
− | ;(5) [[SBS Roof Systems Standard# | + | ;(5) [[SBS Roof Systems Standard#PART_9|'''Primary Membrane''']] and [[SBS Roof Systems Standard#PART_9| '''Membrane Protection''']] |
;(6) '''Mastic''': As approved by manufacturer. | ;(6) '''Mastic''': As approved by manufacturer. | ||
− | ;(7) [[SBS Roof Systems Standard# | + | ;(7) [[SBS Roof Systems Standard#PART_11|'''Roof Drain Membrane Flashing''']]: Onto primed drain flange or adhesive for non-bituminous flexible membrane systems. See also [[SBS Roof Systems Standard#PART_11| '''11.2.1 General''']] for membrane material requirements. |
<hr> | <hr> | ||
=== RELATED WORK BY OTHERS === | === RELATED WORK BY OTHERS === | ||
− | ;(A) [[SBS Roof Systems Standard# | + | ;(A) [[SBS Roof Systems Standard#PART_2|'''Acceptable Supporting Deck Structure''']] |
− | ;(B) [[SBS Roof Systems Standard# | + | ;(B) [[SBS Roof Systems Standard#PART_11|'''Roof Drain Assembly''']] |
* Leader size is determined by using the calculation found in the BC Building Code at Appendix P.7.4.10 and Section 7.4.10.11 (Section 7.4.10.10 for gutters) in conjunction with the 15-minute rainfall value from the National Building Code, Appendix C. | * Leader size is determined by using the calculation found in the BC Building Code at Appendix P.7.4.10 and Section 7.4.10.11 (Section 7.4.10.10 for gutters) in conjunction with the 15-minute rainfall value from the National Building Code, Appendix C. |
Revision as of 18:48, 1 September 2021
Notice to Reader | |
Images used in a Construction Detail are representative and not prescriptive. Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the requirements of the Standard they represent. Unless otherwise required by the Standard, dimensions, the selection of materials and their application remains the responsibility of the Design Authority. The full text of the referenced requirements in the Standard may be read by using the blue hyperlinks |
SBS Details
1 WORK INCLUDED
- (1) Supporting Deck Overlay
- If required by design authority.
- (2) Air or Vapour Control Layers
- If required by design authority.
- (3) Insulation
- See available insulation products in the Accepted Materials section of this Manual.
- (4) Insulation Overlay
- Where required.
- (5) Primary Membrane and Membrane Protection
- (6) Mastic
- As approved by manufacturer.
- (7) Roof Drain Membrane Flashing
- Onto primed drain flange or adhesive for non-bituminous flexible membrane systems. See also 11.2.1 General for membrane material requirements.
2 RELATED WORK BY OTHERS
- Leader size is determined by using the calculation found in the BC Building Code at Appendix P.7.4.10 and Section 7.4.10.11 (Section 7.4.10.10 for gutters) in conjunction with the 15-minute rainfall value from the National Building Code, Appendix C.
NOTE: See the Standard for additional requirements.
Back to "SBS" Roof System Details
© RCABC 2024
RoofStarTM is a registered Trademark of the RCABC.
No reproduction of this material, in whole or in part, is lawful without the expressed permission of the RCABC Guarantee Corp.