− | ;(1) | + | ;(1) '''Supporting Deck Overlay''': Recommended over steel decks, to provide continuous support for membrane control layers (this fulfills the requirement for continuity, ''British Columbia Building Code'', Div. B, '''5.4.1.2''' ('''3''')). |
− | ;(2) | + | ;(2) '''Air or Vapour Controls''': Self-adhering membrane (typical). |
− | ;(3) | + | ;(3) '''Metal Support''': For fully or intermittently unsupported side or end laps. Use pre-finished galvanized steel (min. 24 Ga.), fabricated at least 100 mm (4”) wider than membrane overlaps, and secured with compatible flat-head fasteners (two fasteners per flute, or as otherwise specified). |
− | ;(4) | + | ;(4) '''Long edges (side laps)''':Centre membrane runs along top flutes of steel deck (applicable when no deck overlay is specified and installed). Overlap membrane side laps at least 50 mm (2”), or as specified by the membrane manufacturer (whichever is greater). Side laps must be fully supported by the roof deck or a metal support. |
− | + | ;(5) '''End laps''':Overlap the roll ends at least 100 mm (4”), or as specified by the membrane manufacturer (whichever is greater). End laps must be fully supported by the roof deck or a metal support. | |
− | ;( | ||
<hr> | <hr> |
Revision as of 15:57, 19 May 2022
Division D - Construction Details
TPO 6.3.1 Air and Vapour Controls (field)
Notice to Reader | |
Images used in a Construction Detail are representative and not prescriptive. Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the requirements of the Standard they represent. Unless otherwise required by the Standard, dimensions, the selection of materials and their application remains the responsibility of the Design Authority. The full text of the referenced requirements in the Standard may be read by using the blue hyperlinks |
TPO Details
1 WORK INCLUDED
- (1) Supporting Deck Overlay
- Recommended over steel decks, to provide continuous support for membrane control layers (this fulfills the requirement for continuity, British Columbia Building Code, Div. B, 5.4.1.2 (3)).
- (2) Air or Vapour Controls
- Self-adhering membrane (typical).
- (3) Metal Support
- For fully or intermittently unsupported side or end laps. Use pre-finished galvanized steel (min. 24 Ga.), fabricated at least 100 mm (4”) wider than membrane overlaps, and secured with compatible flat-head fasteners (two fasteners per flute, or as otherwise specified).
- (4) Long edges (side laps)
- Centre membrane runs along top flutes of steel deck (applicable when no deck overlay is specified and installed). Overlap membrane side laps at least 50 mm (2”), or as specified by the membrane manufacturer (whichever is greater). Side laps must be fully supported by the roof deck or a metal support.
- (5) End laps
- Overlap the roll ends at least 100 mm (4”), or as specified by the membrane manufacturer (whichever is greater). End laps must be fully supported by the roof deck or a metal support.
2 RELATED WORK BY OTHERS
- (A) Acceptable Deck
NOTE: See the Standard for additional requirements.