Difference between revisions of "EPDM Conventionally Insulated System (Typical)"

Jump to: navigation, search

Difference between revisions of "EPDM Conventionally Insulated System (Typical)"

(WORK INCLUDED)
 
(31 intermediate revisions by the same user not shown)
Line 1: Line 1:
'''NOTE''': This page is under construction.  Refer to the [[SBS Construction Details|'''SBS Membrane Construction Details''']] for similar application illustrations and requirements.
+
{{Template:RPM Info}}
  
 +
{{DISPLAYTITLE:<span style="position: absolute; clip: rect(1px 1px 1px 1px); clip: rect(1px, 1px, 1px, 1px);">{{FULLPAGENAME}}</span>}}
 +
__NOTOC__
  
 +
<big><big>Division D - Construction Details</big></big>
 
<hr>
 
<hr>
 +
<big><big><big><big><big>EPDM | Conventionally Insulated System (Typical) ([[EPDM_Roof_Systems_Standard#1.1.3.1._Permitted_Roof_Systems | Article 1.1.3.1.]])</big></big></big></big></big>
 +
{{Template:Construction Details Header}}
 +
<div class="panel panel-success">
 +
<div class="panel-heading"><big>'''EPDM Details'''</big></div>
 +
<div class="panel-body">
 +
<div class="col-md-6">
 +
<div style="text-align:center; vertical-align:center">
 +
[[File:6.3.1.1.jpg|class=img-responsive]]
 +
</div>
 +
</div><!-- COL-MD-6 -->
  
 +
<div class="col-md-6">
 +
=== WORK INCLUDED ===
 +
;1) [[EPDM Roof Systems Standard#PART_5|'''Gypsum Deck Overlay''']]: May be required depending on insulation thickness  or when required as a thermal barrier by design authority.
 +
;(2) [[EPDM Roof Systems Standard#PART_7|'''Insulation''']]: Mechanically attached. Installed according to ''RoofStar Guarantee Standards''. See available insulation products in the [[Division C | Division C]] of this Manual.
 +
;(3) [[EPDM Roof Systems Standard#PART_9|'''Single-ply Membrane''']]: Installed according to manufacturer's instructions and ''RoofStar Guarantee Standards''.
 +
;(4) [[EPDM Roof Systems Standard#PART_9|'''Adhesive''']]: Proprietary, installed according to manufacturer's instructions, usually brushed, rolled or sprayed.
 +
;(5) [[EPDM Roof Systems Standard#PART_10|'''Membrane Flashing''']]: Adhered according to manufacturer's printed specifications using proprietary adhesive. Must be carried to outside of parapet or minimum 200 mm (8") above finished roof surface.
 +
;(6) '''Fasteners''': Install according to manufacturer's instructions (style may vary depending on material type and manufacturer's specification).
 +
;(7) '''Membrane Lap''': EPDM (thermoset) membrane may be joined using uncured tape or proprietary adhesive.
 +
;(8) [[EPDM Roof Systems Standard#PART_13|'''Metal Cap Flashing''']]: As required by the ''RoofStar Guarantee Standards''.
  
 +
<hr>
  
[[Section:D. Application: Low Slope Roofs|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''EPDM Application'']]
+
=== RELATED WORK BY OTHERS ===
 +
;(A) [[EPDM Roof Systems Standard#PART_2|'''Acceptable Deck''']]
 +
;(B) Acceptable Parapet Surface: Surface must be smooth, dry and clean. Rough surface must be covered with treated plywood, to be determined by design authority or inspector or as required by manufacturer.
 +
;(C) Sloped Wood Blocking
 +
</div><!-- COL-6-MD -->
 +
</div><!-- PANEL BODY -->
 +
</div><!-- PANEL -->
 +
 
 +
'''NOTE''': See the [[EPDM Roof Systems Standard | '''Standard''']] for additional requirements.
 +
 
 +
<hr>
  
 
[[EPDM (Thermoset Membranes) Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''EPDM Construction Details'']]
 
[[EPDM (Thermoset Membranes) Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''EPDM Construction Details'']]
  
[[Section:G. Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''Construction Details'']]
+
[[Main Page | <i class="fa fa-home fa"></i> Home]]
 +
 
 +
{{Tempate:RPM Page Footer with Copyright and Current Date}}

Latest revision as of 21:52, 27 June 2022



Division D - Construction Details


EPDM | Conventionally Insulated System (Typical) ( Article 1.1.3.1.)

Notice to Reader
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).

The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text.

EPDM Details

6.3.1.1.jpg

1 WORK INCLUDED

1) Gypsum Deck Overlay
May be required depending on insulation thickness or when required as a thermal barrier by design authority.
(2) Insulation
Mechanically attached. Installed according to RoofStar Guarantee Standards. See available insulation products in the Division C of this Manual.
(3) Single-ply Membrane
Installed according to manufacturer's instructions and RoofStar Guarantee Standards.
(4) Adhesive
Proprietary, installed according to manufacturer's instructions, usually brushed, rolled or sprayed.
(5) Membrane Flashing
Adhered according to manufacturer's printed specifications using proprietary adhesive. Must be carried to outside of parapet or minimum 200 mm (8") above finished roof surface.
(6) Fasteners
Install according to manufacturer's instructions (style may vary depending on material type and manufacturer's specification).
(7) Membrane Lap
EPDM (thermoset) membrane may be joined using uncured tape or proprietary adhesive.
(8) Metal Cap Flashing
As required by the RoofStar Guarantee Standards.

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
(B) Acceptable Parapet Surface
Surface must be smooth, dry and clean. Rough surface must be covered with treated plywood, to be determined by design authority or inspector or as required by manufacturer.
(C) Sloped Wood Blocking

NOTE: See the Standard for additional requirements.


Back to EPDM Construction Details

Home

© RCABC 2024
RoofStarTM is a registered Trademark of the RCABC.
No reproduction of this material, in whole or in part, is lawful without the expressed permission of the RCABC Guarantee Corp.