<big><big><big><big><big>SBS 14.3.3 Structures and Equipment (planter pre-curb)</big></big></big></big></big>
+
<big><big><big><big><big>SBS | Structural Planter ([[SBS_Roof_Systems_Standard#14.3.2.7._Structures_and_Equipment | Article 14.3.2.7.]])</big></big></big></big></big>
{| class="wikitable" | style="color: black; background-color: orange; width: 100%;text-align:center"
+
{{Template:Construction Details Header}}
| colspan="2"  | <big>'''''Notice to Reader'''''</big>
 
|-
 
| style="color: black; background-color: #ffffcc; width: 100%;text-align:center" | Images used in a Construction Detail are representative and not prescriptive.  Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the requirements of the Standard they represent. Unless otherwise required by the Standard, dimensions, the selection of materials and their application remains the responsibility of the ''Design Authority''.<br><br>The full text of the referenced requirements in the [[SBS Roof Systems Standard | '''Standard''']] may be read by using the <span style="color:#6495ed">'''blue hyperlinks'''</span>
 
|}
 
 
<div class="panel panel-success">
 
<div class="panel panel-success">
 
<div class="panel-heading"><big>'''SBS Details'''</big></div>
 
<div class="panel-heading"><big>'''SBS Details'''</big></div>
Line 22: Line 18:
 
</div>
 
</div>
  
::Click below for a printable version of this page.
 
 
<div style="width:150px; text-align: left;">
 
:[[File:Pdf.png|100 px|link=http://rpm.rcabc.org/images/7/7e/D1.7.6-5_Print_Sheet.pdf|'''Print Sheet''']]
 
</div>
 
 
</div><!-- COL-MD-6 -->
 
</div><!-- COL-MD-6 -->
  

Latest revision as of 18:21, 27 October 2023



Division D - Construction Details


SBS | Structural Planter ( Article 14.3.2.7.)

Notice to Reader
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).

The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text.

SBS Details

D1.7.6-5 (1).jpg

D1.7.6-5 (2).jpg

1 WORK INCLUDED

(1) Primer
Application method and coverage rate as approved by Primary Membrane Manufacturer.
(2) Primary Roof Membrane
Modified Bituminous base and cap sheet membranes installed as per manufacturer's published application specifications.
(3) Pre-Curb (Start-Up Curb) Membrane Flashing
Modified Bituminous base and cap sheet membrane flashing installed as per manufacturer's published application specifications.
(4) Proprietary Liquid Membrane Flashing
RoofStar Guarantee Program accepted Liquid Membrane Flashing System(s) or hot melt SBS modified bitumen. (NOTE: Refer to Liquid Membrane Flashing Systems in Division C of this Manual). Install as per Manufacturer's published instructions.
(5) Inside Planter Wall Membrane Flashing
Adhered according to manufacturer's specifications using cold adhesive, self-adhered or torch-applied membrane. Torching directly to wood surfaces is not permitted. Carry membrane flashing plies to reglet termination near top of planter wall (stagger membrane seal minimum 300mm (6").
(6) Reglet - Metal Counter Flashing
As required by the RoofStar Guarantee Standards. Note that a coping flashing may be paired with the reglet flashing, as illustrated.
(7) Plaza Deck / Planter Interior Assembly
Extruded polystyrene insulation and filter mat over primary roof membranes. Concrete pavers placed above pre-curb membrane flashing height, on proprietary pedestals. Note: membrane flashing is not permitted above pre-curb membrane flashing on plaza deck side of planter walls.

2 RELATED WORK BY OTHERS

(A) Acceptable Supporting Deck Structure
Concrete slab shown. Each planter area must have a drain through the roof deck.
(B) Pre-Curb
Minimum of 100mm (4") in height above concrete deck, smooth dry and clean.
(C) Cast over Concrete Planter Wall
Form on top of membrane sealed Pre-curbs or Start-up curbs.
(D) Re-Bar
Placed at centre of Pre-curb.
(E) Reglet
Premanufactured purpose-made reglet cast in concrete wall or saw-cut.
(F) Alternate Termination
Horizontal Reglet alternative to pre-manufactured purpose-made reglet, cast in concrete wall or saw-cut on vertical surface of inside planter walls.

NOTE: See the Standard for additional requirements.