=== WORK INCLUDED ===
 
=== WORK INCLUDED ===
  
(1) <b>Gypsum Overlay Board: </b>If required by design authority.
+
;(1) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSSUBSTRATES|'''Gypsum Board''']]: If required by design authority.
 
+
;(2) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSVAPOUR|'''Vapour Retarder''']]:If required by design authority.
(2) <b>Vapour Retarder</b>: If required by design authority.
+
;(3) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSINSULATION|'''Insulation''']]:
 
+
:See list of '''[[Section:C. Accepted Materials|Accepted Materials]]'''.
(3) <b>Insulation:</b> See list of accepted materials in Section 2.2.
+
;(4) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSINSULATIONOVERLAY|'''Insulation Overlay Board''']]:
 
+
:As required.
(4) <b>Insulation Overlay</b>: As required. See <i>RGC Guarantee Standard B4.1, B4.2 </i>and<i> C4.1</i>
+
;(5) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSBASE|'''Primary Membrane and Membrane Protection''']]:
 
+
;(6) ;[[RoofStar Guarantee Standards for SBS Roof Systems#SBSSTRIPTERM|'''Membrane Flashing (attachment & termination)''']]:
(5) <b>Primary Membrane and Membrane Protection</b>
+
Mechanically fasten at terminations.  At least one ply must extend over outside edge.
 
+
;(7) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Metal Base Flashing''']]: Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
(6) <b>Membrane Flashing:</b> Mechanically fasten at terminations.  At least one ply must extend over outside edge. See <i>RGC Guarantee Standard A5.6</i>
+
;(8) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Metal Cap Flashing''']]: Must overlap exterior wall finish. </i>Fasten with  concealed clip-type fasteners  <b>or</b> cladding screws evenly spaced between seams.
 
+
;(9) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSWALLTIEIN|'''Wall Tie-in''']]: Minimum 2 mm (0.078") self-adhered  modified bitumen or flexible membrane manufacturers approved detail.
(7)<b> Metal Base Flashing:</b> Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats. See <i>RGC Guarantee Standard A6.9</i>
+
;(10) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Metal Counter-flashing''']]:
 
 
(8) <b>Metal Cap Flashing:</b> Must overlap exterior wall finish. See <i>RGC Guarantee Standard A6.9 </i>Fasten with  concealed clip-type fasteners  <b>or</b> cladding screws evenly spaced between seams. See <i>RGC Guarantee Standard A6.10.</i>
 
 
 
(9) <b>Wall Tie-In Membrane:</b> Minimum 2 mm (0.078") self-adhered  modified bitumen or flexible membrane manufacturer&#8217;s approved detail.
 
 
 
(10) <b>Metal Counter Flashing</b>
 
  
 
=== RELATED WORK BY OTHERS ===
 
=== RELATED WORK BY OTHERS ===
  
(A) <b>Acceptable Deck</b>
+
;(A) [[RoofStar Guarantee Standards for SBS Roof Systems#SBS-STEELDECK|'''Acceptable Deck''']]
 
+
;(B) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSVAPOUR|'''Air/Vapour Seal''']]
(B) <b>Air / Vapour Seal</b>
+
;(C) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSWALLSUB|'''Acceptable Wall Surface''']]
 
+
;(D) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSWOODBLOCKING|'''Wood Blocking''']]
(C) <b>Acceptable Wall Surface</b>
+
;(E) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSSLOPEDWOODBLOCKING|'''Sloped Wood Blocking''']]
 
+
:Required over 100 mm (4") parapet width.
(D) <b>Wood Blocking</b>
+
;(F) [[RoofStar Guarantee Standards for SBS Roof Systems#SBS-STRIPPING|'''Wall Sheathing Membrane''']]: Minimum 1 mm (0.040") self-adhered modified bitumen.
 
+
;(G) <b>Wall Cladding</b>
(E) <b>Sloped Wood Blocking:</b> Required over 100 mm (4") parapet width. See <i>RGC Guarantee Standard A6.9</i>
 
 
 
(F) <b>Wall Sheathing Membrane</b>
 
 
 
(G) <b>Wall Cladding</b>
 
  
  

Revision as of 21:35, 29 July 2016

10.3.1.4.jpg

1 WORK INCLUDED

(1) Gypsum Board
If required by design authority.
(2) Vapour Retarder
If required by design authority.
(3) Insulation
See list of Accepted Materials.
(4) Insulation Overlay Board
As required.
(5) Primary Membrane and Membrane Protection
(6) ;Membrane Flashing (attachment & termination)
Mechanically fasten at terminations.  At least one ply must extend over outside edge.
(7) Metal Base Flashing
Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
(8) Metal Cap Flashing
Must overlap exterior wall finish. Fasten with concealed clip-type fasteners or cladding screws evenly spaced between seams.
(9) Wall Tie-in
Minimum 2 mm (0.078") self-adhered modified bitumen or flexible membrane manufacturers approved detail.
(10) Metal Counter-flashing

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
(B) Air/Vapour Seal
(C) Acceptable Wall Surface
(D) Wood Blocking
(E) Sloped Wood Blocking
Required over 100 mm (4") parapet width.
(F) Wall Sheathing Membrane
Minimum 1 mm (0.040") self-adhered modified bitumen.
(G) Wall Cladding


NOTE: Refer to RGC Guarantee Standards for additional requirements.





Back to SBS Application

Back to SBS Construction Details

Back to Construction Details