(1) <b>Gypsum Underlayment:</b> If required by design authority.
+
;(1) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSSUBSTRATES|'''Gypsum Deck Overlay''']]: If required by design authority.
 
+
;(2) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSVAPOUR|'''Vapour Retarder''']]: If required by design authority.
(2) <b>Vapor Retarder: </b>If required by design authority.
+
;(3) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSINSULATION|'''Insulation''']]: See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual.
 
+
;(4) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSINSULATIONOVERLAY|'''Insulation Overlay Board''']]: Where required.
(3) <b>Insulation:</b> See list of accepted materials in Section 2.2.
+
;(5) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSBASE|'''Primary Membrane and Membrane Protection''']]
 
+
;(6) [[RoofStar Guarantee Standards for SBS Roof Systems#SBS-STRIPPING|'''MembraneFlashing''']]:>
(4) <b>Insulation Overlay:</b> Where required. See <i>RGC Guarantee Standard B4.1, B4.2 </i>and<i> C4.1</i>
+
;(7) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Membrane Counter Flashing''']]
 
+
;(8) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Base Metal Flashing''']]: Mechanically fasten to top of plywood backing. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
(5) <b>Primary Membrane and Membrane Protection</b>
+
;(9) <b>Metal Flashing / Cladding</b>
 
+
;(10)  '''Secondary Metal Cap Flashing''': Joints to be offset from Cap Flashing, <b>OR</b> Water Channeling Clip may be used (See Inset, Section 10.3), <b>OR</b> solder standing seam joints. Do <b><u>NOT</u></b> place combustible materials over top of firewall.
(6) <b>Membrane Flashing</b>
+
;(11) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Metal Cap Flashing''']]: Standing seam joints required.
 
 
(7) <b>Membrane Counter Flashing</b>
 
 
 
(8)<b> Metal Base Flashing: </b>Mechanically fasten to top of plywood backing. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats. See <i>RGC Guarantee Standard A6.9</i>
 
 
 
(9) <b>Metal Flashing / Cladding</b>
 
 
 
(10)  <b>Secondary Metal Cap Flashing:</b> Joints to be offset from Cap Flashing, <b>OR</b> Water Channeling Clip may be used (See Inset, Section 10.3), <b>OR</b> solder standing seam joints. Do <b><u>NOT</u></b> place combustible materials over top of firewall.
 
 
 
(11) <b>Metal Cap Flashing:</b> Standing seam joints required.
 
  
 
=== RELATED WORK BY OTHERS ===
 
=== RELATED WORK BY OTHERS ===
(A) <b>Acceptable Deck</b>
+
;(A) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSDECKS|'''Acceptable Deck''']]
 
+
;(B) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSWALLSUB|'''Acceptable Wall Surface (Plywood)''']]
(B) <b>Plywood</b>
+
;(C) '''Wood Blocking'''
 
+
;(D) '''Grouted Finish''': Sloped surface to promote drainage off cap flashing.
(C) <b>Wood Blocking</b>
 
 
 
(D) <b>Grouted Finish:</b> Sloped surface to promote drainage off cap flashing.
 
  
  

Revision as of 18:16, 4 August 2016

10.3.4.3.jpg

1 WORK INCLUDED

(1) Gypsum Deck Overlay
If required by design authority.
(2) Vapour Retarder
If required by design authority.
(3) Insulation
See available insulation products in the Accepted Materials section of this Manual.
(4) Insulation Overlay Board
Where required.
(5) Primary Membrane and Membrane Protection
(6) MembraneFlashing
>
(7) Membrane Counter Flashing
(8) Base Metal Flashing
Mechanically fasten to top of plywood backing. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
(9) Metal Flashing / Cladding
(10) Secondary Metal Cap Flashing
Joints to be offset from Cap Flashing, OR Water Channeling Clip may be used (See Inset, Section 10.3), OR solder standing seam joints. Do NOT place combustible materials over top of firewall.
(11) Metal Cap Flashing
Standing seam joints required.

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
(B) Acceptable Wall Surface (Plywood)
(C) Wood Blocking
(D) Grouted Finish
Sloped surface to promote drainage off cap flashing.


NOTE: Refer to RGC Guarantee Standards for additional requirements.