=== WORK INCLUDED === | === WORK INCLUDED === | ||
− | ;(1) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSSUBSTRATES|'''Gypsum Deck Overlay''']]: | + | ;(1) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSSUBSTRATES|'''Gypsum Deck Overlay''']]: If required by design authority. |
;(2) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSVAPOUR|'''Vapour Retarder''']]: If required by design authority. | ;(2) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSVAPOUR|'''Vapour Retarder''']]: If required by design authority. | ||
;(3) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSINSULATION|'''Insulation''']]: See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual. | ;(3) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSINSULATION|'''Insulation''']]: See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual. | ||
;(4) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSINSULATIONOVERLAY|'''Insulation Overlay Board''']]: Where required. | ;(4) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSINSULATIONOVERLAY|'''Insulation Overlay Board''']]: Where required. | ||
;(5) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSBASE|'''Primary Membrane and Membrane Protection''']] | ;(5) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSBASE|'''Primary Membrane and Membrane Protection''']] | ||
− | ;(6) [[RoofStar Guarantee Standards for SBS Roof Systems#SBS-STRIPPING|'''MembraneFlashing''']] | + | ;(6) [[RoofStar Guarantee Standards for SBS Roof Systems#SBS-STRIPPING|'''MembraneFlashing''']] |
;(7) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Membrane Counter Flashing''']] | ;(7) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Membrane Counter Flashing''']] | ||
;(8) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Base Metal Flashing''']]: Mechanically fasten to top of plywood backing. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats. | ;(8) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Base Metal Flashing''']]: Mechanically fasten to top of plywood backing. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats. | ||
Line 13: | Line 13: | ||
;(10) '''Secondary Metal Cap Flashing''': Joints to be offset from Cap Flashing, <b>OR</b> Water Channeling Clip may be used (See inset for detail [[SBS Details:D1.7.19 Roof-Wall Transitions (Fire Separation Wall)|'''D1.7.19 Roof-Wall Transitions (Fire Separation Wall)''']]), <b>OR</b> solder standing seam joints. Do <b><u>NOT</u></b> place combustible materials over top of firewall. | ;(10) '''Secondary Metal Cap Flashing''': Joints to be offset from Cap Flashing, <b>OR</b> Water Channeling Clip may be used (See inset for detail [[SBS Details:D1.7.19 Roof-Wall Transitions (Fire Separation Wall)|'''D1.7.19 Roof-Wall Transitions (Fire Separation Wall)''']]), <b>OR</b> solder standing seam joints. Do <b><u>NOT</u></b> place combustible materials over top of firewall. | ||
;(11) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Metal Cap Flashing''']]: Standing seam joints required. | ;(11) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Metal Cap Flashing''']]: Standing seam joints required. | ||
+ | |||
+ | <hr> | ||
=== RELATED WORK BY OTHERS === | === RELATED WORK BY OTHERS === |
Revision as of 19:21, 4 August 2016
1 WORK INCLUDED
- (1) Gypsum Deck Overlay
- If required by design authority.
- (2) Vapour Retarder
- If required by design authority.
- (3) Insulation
- See available insulation products in the Accepted Materials section of this Manual.
- (4) Insulation Overlay Board
- Where required.
- (5) Primary Membrane and Membrane Protection
- (6) MembraneFlashing
- (7) Membrane Counter Flashing
- (8) Base Metal Flashing
- Mechanically fasten to top of plywood backing. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
- (9) Metal Flashing / Cladding
- (10) Secondary Metal Cap Flashing
- Joints to be offset from Cap Flashing, OR Water Channeling Clip may be used (See inset for detail D1.7.19 Roof-Wall Transitions (Fire Separation Wall)), OR solder standing seam joints. Do NOT place combustible materials over top of firewall.
- (11) Metal Cap Flashing
- Standing seam joints required.
2 RELATED WORK BY OTHERS
- (A) Acceptable Deck
- (B) Acceptable Wall Surface (Plywood)
- (C) Wood Blocking
- (D) Grouted Finish
- Sloped surface to promote drainage off cap flashing.
NOTE: Refer to RGC Guarantee Standards for additional requirements.