(WORK INCLUDED)
(RELATED WORK BY OTHERS)
Line 20: Line 20:
  
  
'''NOTE''': Refer to <i>RGC Guarantee Standards</i> for additional requirements.
+
'''NOTE''': Refer to '''''RoofStar Guarantee Standards''''' for additional requirements.
  
  

Revision as of 20:46, 5 August 2016

10.3.4.4.jpg

1 WORK INCLUDED

(1) Primary Roof Membrane
(2) Base Sheet Flashing
(3) Non-combustible Insulation
Optional (For condensation control) Cellular glass board insulation complying to ASTM C552-00 OR mineral fiber insulation conforming to CAN / CGSB 51.31-M84 and ASTM E84.
(4) Base Metal Flashing
S-Lock joints and concealed discontinuous clips required. Do not fasten to block firewall. (Optional – Metal base flashing may be installed on lower wall area.)
(5) Water Channeling Clip
(See inset) Concealed clip designed with ribs to channel water under standing seam joint with notch to allow water to escape, OR standing seam joints to be soldered, OR an additional layer of metal flashing with offsetting joints. Do NOT place combustible materials over top of firewall.
(6) Metal Cap Flashing
Standing seam joints and concealed continuous or discontinuous clips required.

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
(B) Cant
(C) Acceptable Wall Surface - Plywood
(D) Wood Frame Wall
(E) Block or Concrete Firewall
(F) Sloping Mortar


NOTE: Refer to RoofStar Guarantee Standards for additional requirements.





Back to SBS Application

Back to SBS Construction Details

Back to Construction Details