Difference between revisions of "EPDM Conventionally Insulated System (Typical)"

Jump to: navigation, search

Difference between revisions of "EPDM Conventionally Insulated System (Typical)"

Line 1: Line 1:
'''NOTE''': This page is under construction. Refer to the [[SBS Construction Details|'''SBS Membrane Construction Details''']] for similar application illustrations and requirements.
+
[[File:6.3.1.1.jpg]]
 +
 
 +
 
 +
=== WORK INCLUDED ===
 +
;1) [[RoofStar Guarantee Standards for EPDM Roof Systems#EPDMSUBSTRATES|'''Gypsum Deck Overlay''']]: May be required depending on insulation thickness  or when required as a thermal barrier by design authority.
 +
;(2) [[RoofStar Guarantee Standards for EPDM Roof Systems#EPDMINSULATION|'''Insulation''']]: Mechanically attached. Installed according to ''RoofStar Guarantee Standards''. See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual.
 +
;(3) [[RoofStar Guarantee Standards for EPDM Roof Systems#EPDMMEMBRANE|'''Single-ply Membrane''']]: Installed according to manufacturer's instructions and ''RoofStar Guarantee Standards''.
 +
;(4) [[RoofStar Guarantee Standards for EPDM Roof Systems#EPDMADHESIVE|'''Adhesive''']]: Proprietary, installed according to manufacturer's instructions, usually brushed, rolled or sprayed.
 +
;(5) [[RoofStar Guarantee Standards for EPDM Roof Systems#EPDMSTRIPPING|'''Membrane Flashing''']]: Adhered according to manufacturer's printed specifications using proprietary adhesive. Must be carried to outside of parapet or minimum 200 mm (8") above finished roof surface.
 +
;(6) '''Fasteners''': Install according to manufacturer's instructions (style may vary depending on material type and manufacturer's specification).
 +
;(7) '''Membrane Lap''': EPDM (thermoset) membrane may be joined using uncured tape or proprietary adhesive.
 +
;(8) [[RoofStar Guarantee Standards for EPDM Roof Systems#METALCAP-EPDM|'''Metal Cap Flashing''']]: As required by the ''RoofStar Guarantee Standards''.
 +
 
 +
<hr>
 +
 
 +
=== RELATED WORK BY OTHERS ===
 +
;(A) [[RoofStar Guarantee Standards for EPDM Roof Systems#EPDMDECKS|'''Acceptable Deck''']]
 +
;(B) [[RoofStar Guarantee Standards for EPDM Roof Systems#EPDMWALLSUB|'''Acceptable Parapet Surface''']]: Surface must be smooth, dry and clean. Rough surface must be covered with treated plywood, to be determined by design authority or inspector or as required by manufacturer.
 +
;(C) [[RoofStar Guarantee Standards for EPDM Roof Systems#EPDMWOODBLOCKING|'''Sloped Wood Blocking''']]
 +
 
 +
 
 +
'''NOTE''': Refer to '''''RoofStar Guarantee Standards''''' for additional requirements.
  
  

Revision as of 18:04, 8 August 2016

6.3.1.1.jpg


1 WORK INCLUDED

1) Gypsum Deck Overlay
May be required depending on insulation thickness or when required as a thermal barrier by design authority.
(2) Insulation
Mechanically attached. Installed according to RoofStar Guarantee Standards. See available insulation products in the Accepted Materials section of this Manual.
(3) Single-ply Membrane
Installed according to manufacturer's instructions and RoofStar Guarantee Standards.
(4) Adhesive
Proprietary, installed according to manufacturer's instructions, usually brushed, rolled or sprayed.
(5) Membrane Flashing
Adhered according to manufacturer's printed specifications using proprietary adhesive. Must be carried to outside of parapet or minimum 200 mm (8") above finished roof surface.
(6) Fasteners
Install according to manufacturer's instructions (style may vary depending on material type and manufacturer's specification).
(7) Membrane Lap
EPDM (thermoset) membrane may be joined using uncured tape or proprietary adhesive.
(8) Metal Cap Flashing
As required by the RoofStar Guarantee Standards.

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
(B) Acceptable Parapet Surface
Surface must be smooth, dry and clean. Rough surface must be covered with treated plywood, to be determined by design authority or inspector or as required by manufacturer.
(C) Sloped Wood Blocking


NOTE: Refer to RoofStar Guarantee Standards for additional requirements.




Back to EPDM Application

Back to EPDM Construction Details

Back to Construction Details