Difference between revisions of "SBS Metal Edge Termination"
Difference between revisions of "SBS Metal Edge Termination"
Line 1: | Line 1: | ||
+ | {| class="wikitable" | style="color: black; background-color: orange; width: 100%;text-align:center" | ||
+ | | colspan="2" | <big>To read '''''RoofStar Guarantee Standards''''' for any element in this illustration, click on the <span style="color:#6495ed">'''blue-linked'''</span> terms</big> | ||
+ | |} | ||
<div class="panel panel-success"> | <div class="panel panel-success"> | ||
<div class="panel-heading"><big>'''SBS Details'''</big></div> | <div class="panel-heading"><big>'''SBS Details'''</big></div> |
Revision as of 20:59, 25 August 2016
To read RoofStar Guarantee Standards for any element in this illustration, click on the blue-linked terms |
SBS Details
1 WORK INCLUDED
- (1) Vapour Retarder
- If required by design authority
- (2) Insulation
- See available insulation products in the Accepted Materials section of this Manual.
- (3) Insulation Overlay Board
- Where required.
- (4) Primary Membrane and Membrane Protection
- Mechanically fasten to outside face of fascia (C).
- (5) Mastic
- Trowel coating of compatible mastic.
- (6) Metal Edge/Gravel-stop Flashing
- Minimum 100 mm (4") flange onto roof membrane, eave stop maximum 25 mm (1") high: embed in mastic and mechanically fasten alternately between centre and edge of flange at 100 mm (4") o/c; lap flashing 100 mm (4") minimum.
- (7) Membrane Flashing
- Asphalt and gravel roofing systems, 2 overlapping plies of a minimum 2 mm reinforced SBS modified bitumen base sheet or minimum 180 g / m² polyester felt. For flexible membrane systems, refer to manufacturer’s application details and RoofStar Guarantee Standards.
- (8) Asphalt
- For asphalt and gravel built-up roofing systems only.
- (9) Gravel
- For asphalt and gravel built-up roofing systems only.
2 RELATED WORK BY OTHERS
- (A) Acceptable Deck
- (B) Wood Blocking
- (C) Wood Fascia
NOTE: Refer to RoofStar Guarantee Standards for additional requirements.