Difference between revisions of "SBS Open-wall Scupper Drain"

Jump to: navigation, search

Difference between revisions of "SBS Open-wall Scupper Drain"

(WORK INCLUDED)
 
(11 intermediate revisions by the same user not shown)
Line 1: Line 1:
{| class="wikitable" | style="color: black; background-color: orange; width: 100%;text-align:center"
+
{{Template:RPM Info}}
| colspan="2"  | <big>'''''RoofStar Guarantee Standards''''' are <span style="color:#6495ed">'''blue-linked'''</span></big>
+
 
|}
+
{{DISPLAYTITLE:<span style="position: absolute; clip: rect(1px 1px 1px 1px); clip: rect(1px, 1px, 1px, 1px);">{{FULLPAGENAME}}</span>}}
 +
__NOTOC__
 +
 
 +
<big><big>Division D - Construction Details</big></big>
 +
<hr>
 +
<big><big><big><big><big>SBS | Open-wall Scupper Drain ([[SBS_Roof_Systems_Standard#11.3.3.7._Scuppers_and_Overflows | Article 11.3.3.7.]])</big></big></big></big></big>
 +
{{Template:Construction Details Header}}
 
<div class="panel panel-success">
 
<div class="panel panel-success">
 
<div class="panel-heading"><big>'''SBS Details'''</big></div>
 
<div class="panel-heading"><big>'''SBS Details'''</big></div>
Line 7: Line 13:
 
<div class="col-md-6">
 
<div class="col-md-6">
 
<div style="text-align:center; vertical-align:center">
 
<div style="text-align:center; vertical-align:center">
[[File:10.3.6.4.gif|class=img-responsive]]
+
[[File:10.3.6.4.gif| link=http://rpm.rcabc.org/images/6/6d/10.3.6.4.gif | class=img-responsive]]
 
</div>
 
</div>
 
</div><!-- COL-MD-6 -->
 
</div><!-- COL-MD-6 -->
Line 13: Line 19:
 
<div class="col-md-6">
 
<div class="col-md-6">
 
=== WORK INCLUDED ===
 
=== WORK INCLUDED ===
;(1) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSAIRVAPOUR|'''Air or Vapour Control Layers''']]: If required by design authority.
+
;(1) [[SBS Roof Systems Standard#PART_6|'''Air or Vapour Control Layers''']]: If required by design authority.
;(2) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATION|'''Insulation''']]: Mechanically fastened.  See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual.
+
;(2) [[SBS Roof Systems Standard#PART_7|'''Insulation''']]: Mechanically fastened.  See available insulation products in the [[Division C| Accepted Materials]] Division of this ''Manual''.
;(3) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATIONOVERLAY|'''Insulation Overlay''']]: Where required.
+
;(3) [[SBS Roof Systems Standard#PART_8|'''Insulation Overlay''']]: Where required.
;(4) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSBASE|'''Primary Membrane''']] and [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSPROTECTION| '''Membrane Protection''']]
+
;(4) [[SBS Roof Systems Standard#PART_9|'''Primary Membrane''']] and [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSPROTECTION| '''Membrane Protection''']]
;(5) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSSSCUPPERMATERIALS| '''Metal Scupper with Hopper''']]: The outside face of scupper to be 37.7mm (1&#189;") <b><u>lower</u></b><u> </u>than the box height with a 12.7mm (&#189;") drip edge. Installed in a thin bed of compatible mastic. Interface between outside wall and scupper should be caulked with appropriate sealant. Installed when wall finish is complete prior to completion of roofing or sheet metal (e.g.:  re-roofing).
+
;(5) [[SBS Roof Systems Standard#PART_11| '''Metal Scupper with Hopper''']]: The outside face of scupper to be 37.7mm (1&#189;") <b><u>lower</u></b><u> </u>than the box height with a 12.7mm (&#189;") drip edge. Installed in a thin bed of compatible mastic. Interface between outside wall and scupper should be caulked with appropriate sealant. Installed when wall finish is complete prior to completion of roofing or sheet metal (e.g.:  re-roofing).
 
;(6) '''Scupper Membrane Flashing'''
 
;(6) '''Scupper Membrane Flashing'''
 
;(7) '''Membrane Flashing'''
 
;(7) '''Membrane Flashing'''
;(8) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#METALCAP-SBS|'''Base Metal Flashing''']]: Mechanically fastened. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
+
;(8) [[SBS Roof Systems Standard#PART_13|'''Base Metal Flashing''']]: Mechanically fastened. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
;(9) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#METALCAP-SBS|'''Metal Cap Flashing''']]: Fasten with continuous concealed clip-type fasteners or cladding screws evenly spaced between seams. Flashing 8 and 9 may be one piece.
+
;(9) [[SBS Roof Systems Standard#PART_13|'''Metal Cap Flashing''']]: Fasten with continuous concealed clip-type fasteners or cladding screws evenly spaced between seams. Flashing 8 and 9 may be one piece.
  
 
<hr>
 
<hr>
  
 
=== RELATED WORK BY OTHERS ===
 
=== RELATED WORK BY OTHERS ===
;(A) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSDECKS|'''Acceptable Supporting Deck Structure''']]
+
;(A) [[SBS Roof Systems Standard#PART_2|'''Acceptable Supporting Deck Structure''']]
 
;(B) '''Air / Vapour Seal'''
 
;(B) '''Air / Vapour Seal'''
 
;(C) '''Wood Blocking'''
 
;(C) '''Wood Blocking'''
;(D) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSWALLSUB|'''Acceptable Wall Surface - Plywood''']]: Conform to the requirements for Walls in '''2.6.2 Materials'''.
+
;(D) [[SBS Roof Systems Standard#PART_2|'''Acceptable Wall Surface - Plywood''']]: Conform to the requirements for Walls in '''2.6.2 Materials'''.
;(E) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSWALLSUB|'''Wall Finish''']]: Interface between outside wall and scupper to be caulked with appropriate sealant. Installed by trade responsible for outside wall finish if roofing and metal flashing has been completed prior to exterior wall finish.
+
;(E) [[SBS Roof Systems Standard#PART_10|'''Wall Finish''']]: Interface between outside wall and scupper to be caulked with appropriate sealant. Installed by trade responsible for outside wall finish if roofing and metal flashing has been completed prior to exterior wall finish.
 
</div><!-- COL-6-MD -->
 
</div><!-- COL-6-MD -->
 
</div><!-- PANEL BODY -->
 
</div><!-- PANEL BODY -->
 
</div><!-- PANEL -->
 
</div><!-- PANEL -->
  
'''NOTE''': Refer to '''''RoofStar Guarantee Standards''''' for additional requirements.
+
'''NOTE''': See the [[SBS Roof Systems Standard | '''Standard''']] for additional requirements.
 
 
  
 
<hr>
 
<hr>
  
 +
[[SBS Roof System Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''"SBS" Roof System Details'']]
  
[[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies |<i class="fa fa-chevron-circle-left fa" ></i> Back to ''RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies'']]
+
[[Main Page | <i class="fa fa-home fa"></i> Home]]
 
 
[[SBS Modified Bitumen Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''SBS Modified Bitumen Construction Details'']]
 
  
[[Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''Construction Details'']]
+
{{Tempate:RPM Page Footer with Copyright and Current Date}}

Latest revision as of 18:14, 27 October 2023



Division D - Construction Details


SBS | Open-wall Scupper Drain ( Article 11.3.3.7.)

Notice to Reader
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).

The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text.

SBS Details

10.3.6.4.gif

1 WORK INCLUDED

(1) Air or Vapour Control Layers
If required by design authority.
(2) Insulation
Mechanically fastened. See available insulation products in the Accepted Materials Division of this Manual.
(3) Insulation Overlay
Where required.
(4) Primary Membrane and Membrane Protection
(5) Metal Scupper with Hopper
The outside face of scupper to be 37.7mm (1½") lower than the box height with a 12.7mm (½") drip edge. Installed in a thin bed of compatible mastic. Interface between outside wall and scupper should be caulked with appropriate sealant. Installed when wall finish is complete prior to completion of roofing or sheet metal (e.g.: re-roofing).
(6) Scupper Membrane Flashing
(7) Membrane Flashing
(8) Base Metal Flashing
Mechanically fastened. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
(9) Metal Cap Flashing
Fasten with continuous concealed clip-type fasteners or cladding screws evenly spaced between seams. Flashing 8 and 9 may be one piece.

2 RELATED WORK BY OTHERS

(A) Acceptable Supporting Deck Structure
(B) Air / Vapour Seal
(C) Wood Blocking
(D) Acceptable Wall Surface - Plywood
Conform to the requirements for Walls in 2.6.2 Materials.
(E) Wall Finish
Interface between outside wall and scupper to be caulked with appropriate sealant. Installed by trade responsible for outside wall finish if roofing and metal flashing has been completed prior to exterior wall finish.

NOTE: See the Standard for additional requirements.


Back to "SBS" Roof System Details