Difference between revisions of "SBS Tall Parapet"

Jump to: navigation, search

Difference between revisions of "SBS Tall Parapet"

(WORK INCLUDED)
(WORK INCLUDED)
 
(28 intermediate revisions by the same user not shown)
Line 1: Line 1:
 
{{Template:RPM Info}}
 
{{Template:RPM Info}}
 +
 +
{{DISPLAYTITLE:<span style="position: absolute; clip: rect(1px 1px 1px 1px); clip: rect(1px, 1px, 1px, 1px);">{{FULLPAGENAME}}</span>}}
 +
__NOTOC__
 +
 +
<big><big>Division D - Construction Details</big></big>
 
<hr>
 
<hr>
{| class="wikitable" | style="color: black; background-color: orange; width: 100%;text-align:center"
+
<big><big><big><big><big>SBS | Tall Parapet ([[SBS_Roof_Systems_Standard#10.3.4.1._Parapets | Article 10.3.4.1.]])</big></big></big></big></big>
| colspan="2"  | <big>'''''Notice to Reader'''''</big>
+
{{Template:Construction Details Header}}
|-
 
| style="color: black; background-color: #ffffcc; width: 100%;text-align:center" | Images used in a Construction Detail are representative and not prescriptive. Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the requirements of the Standard they represent. Unless otherwise required by the Standard, dimensions, the selection of materials and their application remains the responsibility of the ''Design Authority''.<br><br>The full text of the referenced requirements in the [[SBS Roof Systems Standard | '''Standard''']] may be read by using the <span style="color:#6495ed">'''blue hyperlinks'''</span>
 
|}
 
 
<div class="panel panel-success">
 
<div class="panel panel-success">
 
<div class="panel-heading"><big>'''SBS Details'''</big></div>
 
<div class="panel-heading"><big>'''SBS Details'''</big></div>
Line 24: Line 26:
 
=== WORK INCLUDED ===
 
=== WORK INCLUDED ===
  
;(1) [[SBS Roof Systems Standard#PART_5|'''Supporting Deck Overlay''']]: If required by design authority.
+
;(1) [[SBS Roof Systems Standard#PART_5|'''Supporting Deck Overlay''']]: If required by ''Design Authority''.
;(2) [[SBS Roof Systems Standard#PART_6|'''Air or Vapour Control Layers''']]: If required by design authority. <html><div data-tooltip="Revised 2021 September 1"></div></html>
+
;(2) [[SBS Roof Systems Standard#PART_6|'''Air or Vapour Control Layers''']]: If required by ''Design Authority''.
;(3) [[SBS Roof Systems Standard#PART_7|'''Insulation''']]: See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual.
+
;(3) [[SBS Roof Systems Standard#PART_7|'''Insulation''']]: See available insulation products in the [[Division C| Accepted Materials]] Division of this ''Manual''.
 
;(4) [[SBS Roof Systems Standard#PART_8|'''Insulation Overlay''']]: As required.  
 
;(4) [[SBS Roof Systems Standard#PART_8|'''Insulation Overlay''']]: As required.  
;(5) [[SBS Roof Systems Standard#PART_9|'''Primary Membrane''']] and [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSPROTECTION| '''Membrane Protection''']]
+
;(5) [[SBS Roof Systems Standard#PART_9|'''Primary Membrane''']]: and membrane protection (See [[SBS Roof Systems Standard#9.1.3.4. Membrane Protection | Article 9.1.3.4.]]).
 
;(6) [[SBS Roof Systems Standard#PART_10|'''Base Membrane Flashing''']]: Mechanically fasten to parapet at termination.
 
;(6) [[SBS Roof Systems Standard#PART_10|'''Base Membrane Flashing''']]: Mechanically fasten to parapet at termination.
;(7) [[SBS Roof Systems Standard#PART_13|'''Base Metal Flashing''']]:  Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.  See '''Section 13.6 - Cap Flashings, Base Flashings and Reglets'''.
+
;(7) [[SBS Roof Systems Standard#PART_13|'''Base Metal Flashing''']]:  Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.  See [[SBS Roof Systems Standard#13.3.2.3. Cap Flashing, Counter-flashing, and Reglet Flashing | Article 13.3.2.3.]]
 
;(8) [[SBS Roof Systems Standard#PART_13|'''Metal Counter Flashing''']]: Minimum 25 mm (1") above roof surface.  
 
;(8) [[SBS Roof Systems Standard#PART_13|'''Metal Counter Flashing''']]: Minimum 25 mm (1") above roof surface.  
;(9) [[SBS Roof Systems Standard#PART_13|'''Metal Cap Flashing''']]: Required whenever the primary roof membrane flashing/stripping is carried over the top of parapet walls. See '''Section 13.6 - Cap Flashings, Base Flashings and Reglets'''.
+
;(9) [[SBS Roof Systems Standard#PART_13|'''Metal Cap Flashing''']]: Required whenever the primary roof membrane flashing/stripping is carried over the top of parapet walls. See [[SBS Roof Systems Standard#13.3.2.3. Cap Flashing, Counter-flashing, and Reglet Flashing | Article 13.3.2.3.]]
  
 
<hr>
 
<hr>

Latest revision as of 17:59, 27 October 2023



Division D - Construction Details


SBS | Tall Parapet ( Article 10.3.4.1.)

Notice to Reader
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).

The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text.

SBS Details

10.3.1.3.jpg

Click below for a printable version of this page.
Print Sheet

1 WORK INCLUDED

(1) Supporting Deck Overlay
If required by Design Authority.
(2) Air or Vapour Control Layers
If required by Design Authority.
(3) Insulation
See available insulation products in the Accepted Materials Division of this Manual.
(4) Insulation Overlay
As required.
(5) Primary Membrane
and membrane protection (See Article 9.1.3.4.).
(6) Base Membrane Flashing
Mechanically fasten to parapet at termination.
(7) Base Metal Flashing
Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats. See Article 13.3.2.3.
(8) Metal Counter Flashing
Minimum 25 mm (1") above roof surface.
(9) Metal Cap Flashing
Required whenever the primary roof membrane flashing/stripping is carried over the top of parapet walls. See Article 13.3.2.3.

2 RELATED WORK BY OTHERS

(A) Acceptable Supporting Deck Structure
(B) Air / Vapour Seal
(C) Acceptable Wall Surface
(D) Wood Blocking
(E) Sloped Wood Blocking
Required over 100 mm (4") parapet width.
(F) Wall Sheathing Membrane
Minimum 1 mm (0.040") self-adhered modified bitumen.
(G) Exterior Wall Finish
(H) Metal Cap Flashing
Required by others whenever the primary roof membrane is not carried over top of the parapet and/or when the wall finish is by others. (Unless specified otherwise).
(I) Cap Flashing Underlay
Minimum 1 mm (0.040" or 40 mil) self-adhered modified bitumen.

NOTE: See the Standard for additional requirements.