Difference between revisions of "SBS Through-wall Scupper Drain"
Difference between revisions of "SBS Through-wall Scupper Drain"
(→WORK INCLUDED) |
|||
(23 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
− | + | {{Template:RPM Info}} | |
+ | {{DISPLAYTITLE:<span style="position: absolute; clip: rect(1px 1px 1px 1px); clip: rect(1px, 1px, 1px, 1px);">{{FULLPAGENAME}}</span>}} | ||
+ | __NOTOC__ | ||
+ | |||
+ | <big><big>Division D - Construction Details</big></big> | ||
+ | <hr> | ||
+ | <big><big><big><big><big>SBS | Through-wall Scupper Drain ([[SBS_Roof_Systems_Standard#11.3.3.7._Scuppers_and_Overflows | Article 11.3.3.7.]])</big></big></big></big></big> | ||
+ | {{Template:Construction Details Header}} | ||
+ | <div class="panel panel-success"> | ||
+ | <div class="panel-heading"><big>'''SBS Details'''</big></div> | ||
+ | <div class="panel-body"> | ||
+ | <div class="col-md-6"> | ||
+ | <div style="text-align:center; vertical-align:center"> | ||
+ | [[File:10.3.6.5.jpg| link=http://rpm.rcabc.org/images/4/42/10.3.6.5.jpg | class=img-responsive]] | ||
+ | </div> | ||
+ | </div><!-- COL-MD-6 --> | ||
+ | |||
+ | <div class="col-md-6"> | ||
=== WORK INCLUDED === | === WORK INCLUDED === | ||
− | ;(1) [[ | + | ;(1) [[SBS Roof Systems Standard#PART_6|'''Air or Vapour Control Layers''']]: If required by design authority. |
− | ;(2) [[ | + | ;(2) [[SBS Roof Systems Standard#PART_7|'''Insulation''']]: See available insulation products in the [[Division C| Accepted Materials]] Division of this ''Manual''. |
− | ;(3) [[ | + | ;(3) [[SBS Roof Systems Standard#PART_8|'''Insulation Overlay''']]: Where required. |
− | ;(4) [[RoofStar Guarantee Standards for SBS Roof | + | ;(4) [[SBS Roof Systems Standard#PART_9|'''Primary Membrane''']] and [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSPROTECTION| '''Membrane Protection''']] |
− | ;(5) [[ | + | ;(5) [[SBS Roof Systems Standard#PART_10|'''Base Membrane Flashing''']] |
− | ;(6) '''Metal Scupper with Hopper''': The outside face of scupper to be minimum 37.7mm (1½") <b><u>lower</u></b><u> </u>than the box height with a 12.7mm (½") drip edge. Installed in a bed of compatible mastic. Interface between outside wall and scupper should be caulked with appropriate sealant. Installed when wall finish is complete prior to completion of roofing or sheet metal (e.g.: re-roofing). | + | ;(6) [[SBS Roof Systems Standard#PART_11| '''Metal Scupper with Hopper''']]: The outside face of scupper to be minimum 37.7mm (1½") <b><u>lower</u></b><u> </u>than the box height with a 12.7mm (½") drip edge. Installed in a bed of compatible mastic. Interface between outside wall and scupper should be caulked with appropriate sealant. Installed when wall finish is complete prior to completion of roofing or sheet metal (e.g.: re-roofing). |
;(7) '''Mastic''': Compatible with membrane | ;(7) '''Mastic''': Compatible with membrane | ||
;(8) '''Scupper Membrane Flashing''': | ;(8) '''Scupper Membrane Flashing''': | ||
− | ;(9) [[ | + | ;(9) [[SBS Roof Systems Standard#PART_13|'''Base Metal Flashing''']]: Mechanically fastened (optional on flexible membrane systems). |
− | ;(10) [[ | + | ;(10)[[SBS Roof Systems Standard#PART_13|'''Metal Counter-flashing''']]: Into reglet approximately 30 mm (1 ¼"). |
<hr> | <hr> | ||
=== RELATED WORK BY OTHERS === | === RELATED WORK BY OTHERS === | ||
− | ;(A) [[ | + | ;(A) [[SBS Roof Systems Standard#PART_2|'''Acceptable Supporting Deck Structure''']] |
;(B) '''Air / Vapour Seal''' | ;(B) '''Air / Vapour Seal''' | ||
− | ;(C) | + | ;(C) '''Wood Blocking''': Optional with insulation cant strips. |
− | ;(D) '''Plywood''': If required by design authority. See | + | ;(D) '''Plywood''': If required by design authority. See the ''RoofStar Guarantee Standards''. |
− | ;(E) [[ | + | ;(E) [[SBS Roof Systems Standard#PART_10|'''Wall Finish''']]: Interface between outside wall and scupper to be caulked with appropriate sealant. Installed by trade responsible for outside wall finish if roofing and metal flashing has been completed prior to exterior wall finish. |
− | + | </div><!-- COL-6-MD --> | |
− | + | </div><!-- PANEL BODY --> | |
− | + | </div><!-- PANEL --> | |
+ | '''NOTE''': See the [[SBS Roof Systems Standard | '''Standard''']] for additional requirements. | ||
<hr> | <hr> | ||
+ | [[SBS Roof System Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''"SBS" Roof System Details'']] | ||
+ | [[Main Page | <i class="fa fa-home fa"></i> Home]] | ||
− | + | {{Tempate:RPM Page Footer with Copyright and Current Date}} | |
− | |||
− | |||
− | |||
− | |||
− |
Latest revision as of 18:15, 27 October 2023
Division D - Construction Details
SBS | Through-wall Scupper Drain ( Article 11.3.3.7.)
Notice to Reader | |
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).
The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text. |
SBS Details
1 WORK INCLUDED
- (1) Air or Vapour Control Layers
- If required by design authority.
- (2) Insulation
- See available insulation products in the Accepted Materials Division of this Manual.
- (3) Insulation Overlay
- Where required.
- (4) Primary Membrane and Membrane Protection
- (5) Base Membrane Flashing
- (6) Metal Scupper with Hopper
- The outside face of scupper to be minimum 37.7mm (1½") lower than the box height with a 12.7mm (½") drip edge. Installed in a bed of compatible mastic. Interface between outside wall and scupper should be caulked with appropriate sealant. Installed when wall finish is complete prior to completion of roofing or sheet metal (e.g.: re-roofing).
- (7) Mastic
- Compatible with membrane
- (8) Scupper Membrane Flashing
- (9) Base Metal Flashing
- Mechanically fastened (optional on flexible membrane systems).
- (10)Metal Counter-flashing
- Into reglet approximately 30 mm (1 ¼").
2 RELATED WORK BY OTHERS
- (A) Acceptable Supporting Deck Structure
- (B) Air / Vapour Seal
- (C) Wood Blocking
- Optional with insulation cant strips.
- (D) Plywood
- If required by design authority. See the RoofStar Guarantee Standards.
- (E) Wall Finish
- Interface between outside wall and scupper to be caulked with appropriate sealant. Installed by trade responsible for outside wall finish if roofing and metal flashing has been completed prior to exterior wall finish.
NOTE: See the Standard for additional requirements.
Back to "SBS" Roof System Details