(WORK INCLUDED)
(WORK INCLUDED)
Line 19: Line 19:
 
;(5) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSBASE|'''Primary Membrane and Membrane Protection''']]
 
;(5) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSBASE|'''Primary Membrane and Membrane Protection''']]
 
;(6) [[RoofStar Guarantee Standards for SBS Roof Systems#SBS-STRIPPING|'''Membrane Flashing''']]:  Mechanically fasten to outside face of parapet blocking (F). Do not mop outside edge. At least one ply must extend over outside edge.
 
;(6) [[RoofStar Guarantee Standards for SBS Roof Systems#SBS-STRIPPING|'''Membrane Flashing''']]:  Mechanically fasten to outside face of parapet blocking (F). Do not mop outside edge. At least one ply must extend over outside edge.
;(7) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Metal Base Flashing''']]: Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.  See '''Section 12.6 - Cap Flashings, Base Flashings and Reglets'''.
+
;(7) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Metal Base Flashing''']]: Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.  See '''Section 13.6 - Cap Flashings, Base Flashings and Reglets'''.
;(8) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Metal Cap Flashing''']]: Flashings 7 and 8 may be one piece. See Section 14.  Fasten with continuous concealed clip-type fasteners <b>or</b> cladding screws evenly spaced between seams. See '''Section 14.3 - Attachment'''.
+
;(8) [[RoofStar Guarantee Standards for SBS Roof Systems#METALCAP-SBS|'''Metal Cap Flashing''']]: Flashings 7 and 8 may be one piece. See Section 14.  Fasten with continuous concealed clip-type fasteners <b>or</b> cladding screws evenly spaced between seams. See '''Section 13.3 - Attachment'''.
  
 
<hr>
 
<hr>

Revision as of 16:39, 1 December 2016

RoofStar Guarantee Standards are blue-linked
SBS Details

10.3.1.2.jpg

1 WORK INCLUDED

(1) Gypsum Deck Overlay
(2) Vapour Retarder
If required by design authority.
(3) Insulation
(4) Insulation Overlay Board
As required.
(5) Primary Membrane and Membrane Protection
(6) Membrane Flashing
Mechanically fasten to outside face of parapet blocking (F). Do not mop outside edge. At least one ply must extend over outside edge.
(7) Metal Base Flashing
Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats. See Section 13.6 - Cap Flashings, Base Flashings and Reglets.
(8) Metal Cap Flashing
Flashings 7 and 8 may be one piece. See Section 14. Fasten with continuous concealed clip-type fasteners or cladding screws evenly spaced between seams. See Section 13.3 - Attachment.

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
(B) Air / Vapour Seal
(C) Acceptable Wall Surface
(D) Wood Blocking
(E) Flexible Insulation
(C) Sloped Wood Blocking
Required over 100 mm (4") parapet width.

NOTE: Refer to RoofStar Guarantee Standards for additional requirements.