Difference between revisions of "SBS Expansion Joint (Wall)"

Jump to: navigation, search

Difference between revisions of "SBS Expansion Joint (Wall)"

(RELATED WORK BY OTHERS)
Line 21: Line 21:
 
<div class="col-md-6">
 
<div class="col-md-6">
 
=== WORK INCLUDED ===
 
=== WORK INCLUDED ===
;(1) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSVAPOUR|'''Vapour Retarder''']]:  The requirement for a vapour retarder is determined by the design authority. Optional terminations.
+
;(1) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSAIRVAPOUR|'''Air or Vapour Control Layers''']]:  The requirement for a vapour retarder is determined by the design authority. Optional terminations.
 
;(2) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATION|'''Insulation''']]
 
;(2) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATION|'''Insulation''']]
 
;(3) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATIONOVERLAY|'''Insulation Overlay''']]:  Where required.
 
;(3) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATIONOVERLAY|'''Insulation Overlay''']]:  Where required.
;(4) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSBASE|'''Primary Membrane and Membrane Protection''']]
+
;(4) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSBASE|'''Primary Membrane''']] and [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSPROTECTION| '''Membrane Protection''']]
 
;(5) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSSTRIPTERM|'''Membrane Flashing''']]: Mechanically fasten to top of wood blocking.
 
;(5) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSSTRIPTERM|'''Membrane Flashing''']]: Mechanically fasten to top of wood blocking.
 
;(6) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#METALCAP-SBS|'''Membrane Counter-flashing''']]: Flashing sealed to wall with compatible mastic.
 
;(6) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#METALCAP-SBS|'''Membrane Counter-flashing''']]: Flashing sealed to wall with compatible mastic.
Line 36: Line 36:
  
 
=== RELATED WORK BY OTHERS ===
 
=== RELATED WORK BY OTHERS ===
;(A) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSDECKS|'''Acceptable Deck''']]
+
;(A) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSDECKS|'''Acceptable Supporting Deck Structure''']]
;(B) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSVAPOUR|'''Air/Vapour Seal''']]: Sealed to wall.
+
;(B) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSAIRVAPOUR|'''Air and Vapour Control Layer Seal''']]: Sealed to wall.
 
;(C) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSWOODBLOCKING|'''Wood Blocking''']]: Height to provide minimum 200 mm (8") above completed roof system, slope top edge.
 
;(C) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSWOODBLOCKING|'''Wood Blocking''']]: Height to provide minimum 200 mm (8") above completed roof system, slope top edge.
 
;(D) <b>Flexible Insulation</b>
 
;(D) <b>Flexible Insulation</b>
;(E) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#METALCAP-SBS|'''Reglet''']]:
+
;(E) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSSTRIPTERM|'''Reglet''']]:
 
;(F)  [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSSLOPEDWOODBLOCKING|'''Sloped Wood Blocking''']]:
 
;(F)  [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSSLOPEDWOODBLOCKING|'''Sloped Wood Blocking''']]:
 
</div><!-- COL-6-MD -->
 
</div><!-- COL-6-MD -->

Revision as of 18:46, 29 January 2019

RoofStar Guarantee Standards are blue-linked
SBS Details

10.3.3.2.jpg


Click below for a printable version of this page.
Print Sheet

1 WORK INCLUDED

(1) Air or Vapour Control Layers
The requirement for a vapour retarder is determined by the design authority. Optional terminations.
(2) Insulation
(3) Insulation Overlay
Where required.
(4) Primary Membrane and Membrane Protection
(5) Membrane Flashing
Mechanically fasten to top of wood blocking.
(6) Membrane Counter-flashing
Flashing sealed to wall with compatible mastic.
(7) Metal Base Flashing
Mechanically fasten to top of wood blocking (C). Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
(8) Metal Counter-flashing
Into reglet approximately 30 mm (1¼") and caulked.
(9) Caulking
(10) Membrane Underlay
Minimum self-adhered modified bitumen membrane.
(11) Metal Cap Flashing
Must overlap exterior wall finish. Fasten with continuous concealed clip-type fasteners or cladding screws evenly spaced between seams.

2 RELATED WORK BY OTHERS

(A) Acceptable Supporting Deck Structure
(B) Air and Vapour Control Layer Seal
Sealed to wall.
(C) Wood Blocking
Height to provide minimum 200 mm (8") above completed roof system, slope top edge.
(D) Flexible Insulation
(E) Reglet
(F) Sloped Wood Blocking

NOTE: Refer to RoofStar Guarantee Standards for additional requirements.




Back to RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies

Back to SBS Modified Bitumen Construction Details

Back to Construction Details