Difference between revisions of "Asphalt Shingles - Valley Intersection with Ridge"

Jump to: navigation, search

Difference between revisions of "Asphalt Shingles - Valley Intersection with Ridge"

(WORK INCLUDED)
(RELATED WORK BY OTHERS)
Line 32: Line 32:
  
 
=== RELATED WORK BY OTHERS ===
 
=== RELATED WORK BY OTHERS ===
;(A) [[RoofStar Guarantee Standards for Asphalt Shingle Systems#AShDECK|'''Acceptable Deck''']]
+
;(A) [[Standard for Asphalt Shingle Systems#AShDECKS|'''Acceptable Deck''']]
 
</div><!-- COL-6-MD -->
 
</div><!-- COL-6-MD -->
 
</div><!-- PANEL BODY -->
 
</div><!-- PANEL BODY -->
Line 42: Line 42:
  
  
[[RoofStar Guarantee Standards for Asphalt Shingle Systems|<i class="fa fa-chevron-circle-left fa" ></i> RoofStar Guarantee Standards for Asphalt Shingle Systems]]
+
[[Standard for Asphalt Shingle Systems|<i class="fa fa-chevron-circle-left fa" ></i> Standard for Asphalt Shingle Systems]]
  
 
[[Asphalt Shingle Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''Asphalt Shingles Construction Details'']]
 
[[Asphalt Shingle Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''Asphalt Shingles Construction Details'']]
  
 
[[Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''Construction Details'']]
 
[[Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''Construction Details'']]

Revision as of 16:49, 8 June 2021

RoofStar Guarantee Standards are blue-linked
Asphalt Shingle Details
Click on any image to expand it
ASh 10.5.1-1 CD.jpg ASh 10.5.1-2 CD.jpg
ASh 10.5.1-3 CD.jpg ASh 10.5.1-4 CD.jpg

1 WORK INCLUDED

(1) Valley Protection Membrane
Applied beneath the metal valley flashing.
(2) Valley Metal Flashing
Required for open valleys.
(3) Underlayment
Required, and installed to overlap the Valley Protection Membrane and the Valley Metal Flashing. Install ‘shingle-style’, following the requirements for side and end laps; use acceptable fasteners, or adhere (if a self-adhering membrane) in keeping with the manufacturer’s published requirements.
(4) Lower Membrane Patch
Required to cover the joint where the ridgeline of one roof joins the sloped plane of another. Cut as illustrated and apply to the slope; the patch must be cut large enough to extend upslope at least 150 mm (6”), but must not exceed the exposure of the ridge cap shingles.
(5) Upper Membrane Patch
Required to overlap the Lower Membrane Patch, ‘shingle-style’, by at least 50 mm (2”). Extend the patch upslope past the Metal Valley Flashing at least 150 mm (6”).
(6) Shingles (field)
(7) Shingle Ridge Cap
(8) Split Ridge Cap Shingle Transition
Required to tie the ridge caps into the adjacent roof field shingles.

2 RELATED WORK BY OTHERS

(A) Acceptable Deck

NOTE: Refer to RoofStar Guarantee Standards for additional requirements.



Standard for Asphalt Shingle Systems

Back to Asphalt Shingles Construction Details