Difference between revisions of "SBS Curb for Multiple Penetrations"

Jump to: navigation, search

Difference between revisions of "SBS Curb for Multiple Penetrations"

Line 1: Line 1:
 +
{| class="wikitable" | style="color: black; background-color: orange; width: 100%;text-align:center"
 +
| colspan="2"  | <big>To read '''''RoofStar Guarantee Standards''''' for any element in this illustration, click on the <span style="color:#6495ed">'''blue-linked'''</span> terms</big>
 +
|}
 
<div class="panel panel-success">
 
<div class="panel panel-success">
 
<div class="panel-heading"><big>'''SBS Details'''</big></div>
 
<div class="panel-heading"><big>'''SBS Details'''</big></div>
Line 34: Line 37:
  
 
<hr>
 
<hr>
 
 
  
  

Revision as of 21:09, 25 August 2016

To read RoofStar Guarantee Standards for any element in this illustration, click on the blue-linked terms
SBS Details

10.3.5.3.jpg

1 WORK INCLUDED

(1) Gypsum Deck Overlay
If required by design authority.
(2) Vapour Retarder
If required by design authority.
(3) Insulation
See available insulation products in the Accepted Materials section of this Manual.
(4) Insulation Overlay Board
As required.
(5) Primary Membrane and Membrane Protection
(6) Membrane Flashing
Mechanically fasten to top of curb (C).
(7) Base Metal Flashing
Mechanically fasten to top of curb, standing seam at corners of cant, optional on flexible membrane systems. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
(8) Metal Counter Flashing
(9) Metal Hood

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
(B) Air / Vapour Seal
(C) Wood Blocking/Curb
Minimum 200 mm (8") and maximum 300 mm (12") above finished roof surface.

NOTE: Refer to RoofStar Guarantee Standards for additional requirements.




Back to SBS Application

Back to SBS Construction Details

Back to Construction Details