Difference between revisions of "ASM Cylindrical Penetration (Split Panel Flashing)"
Difference between revisions of "ASM Cylindrical Penetration (Split Panel Flashing)"
(→WORK INCLUDED) |
|||
Line 23: | Line 23: | ||
;(1) [[RoofStar Guarantee Standards for ASM Roof Assemblies#ASMUNDERLAYMENT|'''Underlayment''']]: The type of underlay required is determined by roof slope. | ;(1) [[RoofStar Guarantee Standards for ASM Roof Assemblies#ASMUNDERLAYMENT|'''Underlayment''']]: The type of underlay required is determined by roof slope. | ||
;(2) [[RoofStar Guarantee Standards for ASM Roof Assemblies#ASMSLIP|'''Slip Sheet''']]: Recommended over asphaltic underlays and / or as required by metal roof panel manufacturer. | ;(2) [[RoofStar Guarantee Standards for ASM Roof Assemblies#ASMSLIP|'''Slip Sheet''']]: Recommended over asphaltic underlays and / or as required by metal roof panel manufacturer. | ||
− | ;(3 | + | ;(3) [[RoofStar Guarantee Standards for ASM Roof Assemblies#ASMPANEL |'''Architectural Metal Roof Panel''']]: Lower, installed prior to the pipe flashing, cut hole large enough to allow for movement. Extend 400 mm (16") upslope beyond the pipe. |
;(4) '''Flashing''': Flange set in two continuous beads of accepted caulking. | ;(4) '''Flashing''': Flange set in two continuous beads of accepted caulking. | ||
;(5) '''Spaced Cleat''': Cleats, set in accepted caulking, spaced 50 mm (2") and fastened with compatible non-corrosive flat head screws. | ;(5) '''Spaced Cleat''': Cleats, set in accepted caulking, spaced 50 mm (2") and fastened with compatible non-corrosive flat head screws. | ||
;(6) '''Architectural Metal Roof Panel''': Upper, installed after installation of pipe flashing. Cut hole for pipe penetration and turn panel end under to accommodate cleats. | ;(6) '''Architectural Metal Roof Panel''': Upper, installed after installation of pipe flashing. Cut hole for pipe penetration and turn panel end under to accommodate cleats. | ||
− | ;(7) ''' | + | ;(7) '''Settlement Cap''': Material must match flashing material. |
;(8) '''Caulking''': Bead of caulking tooled into transition between metal roof panel and flashing. | ;(8) '''Caulking''': Bead of caulking tooled into transition between metal roof panel and flashing. | ||
;(9) '''Sealant Tape''': Two rows of sealant tape or acceptable caulking. | ;(9) '''Sealant Tape''': Two rows of sealant tape or acceptable caulking. |
Revision as of 15:09, 12 January 2018
RoofStar Guarantee Standards are blue-linked |
ASM Details
1 WORK INCLUDED
- (1) Underlayment
- The type of underlay required is determined by roof slope.
- (2) Slip Sheet
- Recommended over asphaltic underlays and / or as required by metal roof panel manufacturer.
- (3) Architectural Metal Roof Panel
- Lower, installed prior to the pipe flashing, cut hole large enough to allow for movement. Extend 400 mm (16") upslope beyond the pipe.
- (4) Flashing
- Flange set in two continuous beads of accepted caulking.
- (5) Spaced Cleat
- Cleats, set in accepted caulking, spaced 50 mm (2") and fastened with compatible non-corrosive flat head screws.
- (6) Architectural Metal Roof Panel
- Upper, installed after installation of pipe flashing. Cut hole for pipe penetration and turn panel end under to accommodate cleats.
- (7) Settlement Cap
- Material must match flashing material.
- (8) Caulking
- Bead of caulking tooled into transition between metal roof panel and flashing.
- (9) Sealant Tape
- Two rows of sealant tape or acceptable caulking.
- (10) Drag-load Fasteners
- Compatible non-corrosive fasteners.
2 RELATED WORK BY OTHERS
- (A) Acceptable Deck
NOTE: Refer to RoofStar Guarantee Standards for additional requirements.
RoofStar Guarantee Standards for ASM Roof Assemblies