=== WORK INCLUDED === | === WORK INCLUDED === | ||
− | ;(1) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies# | + | ;(1) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSAIRVAPOUR|'''Air or Vapour Control Layers''']]: If required by design authority. |
;(2) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATION|'''Insulation''']]: See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual. | ;(2) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATION|'''Insulation''']]: See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual. | ||
− | ;(3) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATIONOVERLAY|'''Insulation Overlay | + | ;(3) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSINSULATIONOVERLAY|'''Insulation Overlay''']]: Where required. |
− | ;(4) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSBASE|'''Primary Membrane and Membrane Protection''']] | + | ;(4) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSBASE|'''Primary Membrane''']] and [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSPROTECTION| '''Membrane Protection''']] |
− | ;(5) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBS-STRIPPING|'''Base | + | ;(5) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBS-STRIPPING|'''Base Membrane Flashing''']] |
− | ;(6) '''Metal Scupper with Hopper''': The outside face of scupper to be minimum 37.7mm (1½") <b><u>lower</u></b><u> </u>than the box height with a 12.7mm (½") drip edge. Installed in a bed of compatible mastic. Interface between outside wall and scupper should be caulked with appropriate sealant. Installed when wall finish is complete prior to completion of roofing or sheet metal (e.g.: re-roofing). | + | ;(6) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSSSCUPPERMATERIALS| '''Metal Scupper with Hopper''']]: The outside face of scupper to be minimum 37.7mm (1½") <b><u>lower</u></b><u> </u>than the box height with a 12.7mm (½") drip edge. Installed in a bed of compatible mastic. Interface between outside wall and scupper should be caulked with appropriate sealant. Installed when wall finish is complete prior to completion of roofing or sheet metal (e.g.: re-roofing). |
;(7) '''Mastic''': Compatible with membrane | ;(7) '''Mastic''': Compatible with membrane | ||
;(8) '''Scupper Membrane Flashing''': | ;(8) '''Scupper Membrane Flashing''': | ||
Line 27: | Line 27: | ||
=== RELATED WORK BY OTHERS === | === RELATED WORK BY OTHERS === | ||
− | ;(A) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSDECKS|'''Acceptable Deck''']] | + | ;(A) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSDECKS|'''Acceptable Supporting Deck Structure''']] |
;(B) '''Air / Vapour Seal''' | ;(B) '''Air / Vapour Seal''' | ||
− | ;(C) | + | ;(C) '''Wood Blocking''': Optional with insulation cant strips. |
;(D) '''Plywood''': If required by design authority. See the ''RoofStar Guarantee Standards''. | ;(D) '''Plywood''': If required by design authority. See the ''RoofStar Guarantee Standards''. | ||
;(E) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSWALLSUB|'''Wall Finish''']]: Interface between outside wall and scupper to be caulked with appropriate sealant. Installed by trade responsible for outside wall finish if roofing and metal flashing has been completed prior to exterior wall finish. | ;(E) [[RoofStar Guarantee Standards for SBS Modified Bitumen Roof Assemblies#SBSWALLSUB|'''Wall Finish''']]: Interface between outside wall and scupper to be caulked with appropriate sealant. Installed by trade responsible for outside wall finish if roofing and metal flashing has been completed prior to exterior wall finish. |
Revision as of 19:47, 30 January 2019
RoofStar Guarantee Standards are blue-linked |
SBS Details
1 WORK INCLUDED
- (1) Air or Vapour Control Layers
- If required by design authority.
- (2) Insulation
- See available insulation products in the Accepted Materials section of this Manual.
- (3) Insulation Overlay
- Where required.
- (4) Primary Membrane and Membrane Protection
- (5) Base Membrane Flashing
- (6) Metal Scupper with Hopper
- The outside face of scupper to be minimum 37.7mm (1½") lower than the box height with a 12.7mm (½") drip edge. Installed in a bed of compatible mastic. Interface between outside wall and scupper should be caulked with appropriate sealant. Installed when wall finish is complete prior to completion of roofing or sheet metal (e.g.: re-roofing).
- (7) Mastic
- Compatible with membrane
- (8) Scupper Membrane Flashing
- (9) Base Metal Flashing
- Mechanically fastened (optional on flexible membrane systems).
- (10) Metal Counter-flashing
- Into reglet approximately 30 mm (1 ¼").
2 RELATED WORK BY OTHERS
- (A) Acceptable Supporting Deck Structure
- (B) Air / Vapour Seal
- (C) Wood Blocking
- Optional with insulation cant strips.
- (D) Plywood
- If required by design authority. See the RoofStar Guarantee Standards.
- (E) Wall Finish
- Interface between outside wall and scupper to be caulked with appropriate sealant. Installed by trade responsible for outside wall finish if roofing and metal flashing has been completed prior to exterior wall finish.
NOTE: Refer to RoofStar Guarantee Standards for additional requirements.