Difference between revisions of "SBS Tall Parapet"
Difference between revisions of "SBS Tall Parapet"
(→WORK INCLUDED) |
(→WORK INCLUDED) |
||
Line 25: | Line 25: | ||
;(1) [[SBS Roof Systems Standard#PART_5|'''Supporting Deck Overlay''']]: If required by design authority. | ;(1) [[SBS Roof Systems Standard#PART_5|'''Supporting Deck Overlay''']]: If required by design authority. | ||
− | ;(2) [[SBS Roof Systems Standard#PART_6|'''Air or Vapour Control Layers''']]: If required by design authority.<html><div data-tooltip="Revised 2021 September 1"></div></html> | + | ;(2) [[SBS Roof Systems Standard#PART_6|'''Air or Vapour Control Layers''']]: If required by design authority. <html><div data-tooltip="Revised 2021 September 1"></div></html> |
;(3) [[SBS Roof Systems Standard#PART_7|'''Insulation''']]: See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual. | ;(3) [[SBS Roof Systems Standard#PART_7|'''Insulation''']]: See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual. | ||
;(4) [[SBS Roof Systems Standard#PART_8|'''Insulation Overlay''']]: As required. | ;(4) [[SBS Roof Systems Standard#PART_8|'''Insulation Overlay''']]: As required. |
Revision as of 17:01, 1 September 2021
Notice to Reader | |
Images used in a Construction Detail are representative and not prescriptive. Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the requirements of the Standard they represent. Unless otherwise required by the Standard, dimensions, the selection of materials and their application remains the responsibility of the Design Authority. The full text of the referenced requirements in the Standard may be read by using the blue hyperlinks |
SBS Details
1 WORK INCLUDED
- (1) Supporting Deck Overlay
- If required by design authority.
- (2) Air or Vapour Control Layers
- If required by design authority.
- (3) Insulation
- See available insulation products in the Accepted Materials section of this Manual.
- (4) Insulation Overlay
- As required.
- (5) Primary Membrane and Membrane Protection
- (6) Base Membrane Flashing
- Mechanically fasten to parapet at termination.
- (7) Base Metal Flashing
- Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats. See Section 13.6 - Cap Flashings, Base Flashings and Reglets.
- (8) Metal Counter Flashing
- Minimum 25 mm (1") above roof surface.
- (9) Metal Cap Flashing
- Required whenever the primary roof membrane flashing/stripping is carried over the top of parapet walls. See Section 13.6 - Cap Flashings, Base Flashings and Reglets.
2 RELATED WORK BY OTHERS
- (A) Acceptable Supporting Deck Structure
- (B) Air / Vapour Seal
- (C) Acceptable Wall Surface
- (D) Wood Blocking
- (E) Sloped Wood Blocking
- Required over 100 mm (4") parapet width.
- (F) Wall Sheathing Membrane
- Minimum 1 mm (0.040") self-adhered modified bitumen.
- (G) Exterior Wall Finish
- (H) Metal Cap Flashing
- Required by others whenever the primary roof membrane is not carried over top of the parapet and/or when the wall finish is by others. (Unless specified otherwise).
- (I) Cap Flashing Underlay
- Minimum 1 mm (0.040" or 40 mil) self-adhered modified bitumen.
NOTE: See the Standard for additional requirements.