+ | <big><big>Division D - Construction Details</big></big> | ||
<hr> | <hr> | ||
+ | <big><big><big><big><big>SBS 11.3.3.2-4 Curbs and Sleepers (multiple penetrations)</big></big></big></big></big> | ||
{| class="wikitable" | style="color: black; background-color: orange; width: 100%;text-align:center" | {| class="wikitable" | style="color: black; background-color: orange; width: 100%;text-align:center" | ||
| colspan="2" | <big>'''''Notice to Reader'''''</big> | | colspan="2" | <big>'''''Notice to Reader'''''</big> |
Revision as of 18:12, 7 September 2021
Division D - Construction Details
SBS 11.3.3.2-4 Curbs and Sleepers (multiple penetrations)
Notice to Reader | |
Images used in a Construction Detail are representative and not prescriptive. Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the requirements of the Standard they represent. Unless otherwise required by the Standard, dimensions, the selection of materials and their application remains the responsibility of the Design Authority. The full text of the referenced requirements in the Standard may be read by using the blue hyperlinks |
SBS Details
1 WORK INCLUDED
- (1) Supporting Deck Overlay
- If required by design authority.
- (2) Air or Vapour Control Layers
- If required by design authority.
- (3) Insulation
- See available insulation products in the Accepted Materials section of this Manual.
- (4) Insulation Overlay
- As required.
- (5) Primary Membrane and Membrane Protection
- (6) Membrane Flashing
- Mechanically fasten to top of curb (C).
- (7) Base Metal Flashing
- Mechanically fasten to top of curb, standing seam at corners of cant, optional on flexible membrane systems. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
- (8) Metal Counter Flashing
- (9) Metal Hood
2 RELATED WORK BY OTHERS
- (A) Acceptable Supporting Deck Structure
- (B) Air / Vapour Seal
- (C) Curb
- Minimum 200 mm (8") above finished roof surface.
NOTE: See the Standard for additional requirements.
Back to "SBS" Roof System Details