Membrane flashing (stripping) details (with the exception of low parapets, cant strip edges and RGC accepted door sill details) must be designed to provide a minimum 200 mm (8") sealed height above the finished roof surfacing. Surfacing is defined as the top of the roofing assembly, be it membrane, ballast or growing medium (soil). All membrane flashing (stripping) terminating on a vertical surface must be mechanically fastened. | Membrane flashing (stripping) details (with the exception of low parapets, cant strip edges and RGC accepted door sill details) must be designed to provide a minimum 200 mm (8") sealed height above the finished roof surfacing. Surfacing is defined as the top of the roofing assembly, be it membrane, ballast or growing medium (soil). All membrane flashing (stripping) terminating on a vertical surface must be mechanically fastened. | ||
Line 6: | Line 6: | ||
Parapet walls may be less than 200 mm (8") in height, but not less than 87.7 mm (3½") in height. | Parapet walls may be less than 200 mm (8") in height, but not less than 87.7 mm (3½") in height. | ||
− | All cant edge and parapet wall details must have membrane flashing (stripping) that overlaps the exterior finish (i.e. wall cladding) by a minimum of 50 mm (2"). On high parapet walls | + | All cant edge and parapet wall details must have membrane flashing (stripping) that overlaps the exterior finish (i.e. wall cladding) by a minimum of 50 mm (2"). On high parapet walls that are completely flashed with metal, where membrane flashing (stripping) is terminated part way up the wall, the remainder of the parapet must be covered with a flashing underlay of a minimum 40 mils or 1 mm (.040") self-adhered modified bitumen membrane. {{hilite | (see Detail Section '''reference needed''') || 2019-April-21 }}. |
All membrane flashing (stripping) terminating at cladded (i.e. stucco, siding, etc.) walls must lap under the sheathing membrane and cladding by minimum of 75 mm (3"). | All membrane flashing (stripping) terminating at cladded (i.e. stucco, siding, etc.) walls must lap under the sheathing membrane and cladding by minimum of 75 mm (3"). | ||
Line 15: | Line 15: | ||
<p class="principles">New construction projects must follow proper sequencing. Where roof flashings overlap work by others (i.e. siding, stucco, etc.), this work must be complete prior to the installation of metal flashing or wood blocking must be installed to facilitate the future installation of the exterior wall finish under the cap flashing. When lapping under work by others (siding, stucco, etc.), the membrane and metal roof flashings must be installed prior to any wall coverings. Any variance to proper detail sequencing must be approved by the design authority in writing ({{hilite | see Section reference needed). || 2018-April-21 }}</p> | <p class="principles">New construction projects must follow proper sequencing. Where roof flashings overlap work by others (i.e. siding, stucco, etc.), this work must be complete prior to the installation of metal flashing or wood blocking must be installed to facilitate the future installation of the exterior wall finish under the cap flashing. When lapping under work by others (siding, stucco, etc.), the membrane and metal roof flashings must be installed prior to any wall coverings. Any variance to proper detail sequencing must be approved by the design authority in writing ({{hilite | see Section reference needed). || 2018-April-21 }}</p> | ||
− | < | + | <span class="principles">{{strike| Use of the reverse lap method must be an acceptable application method to the membrane manufacturer. || 2019-September-30 }}</span> {{hilite | Is this applicable to single-ply membranes? || 2019-September-30 }} |
<p class="principles">If no published instructions are available, specific instructions in writing from the manufacturer must be obtained and filed with RGC before project start-up.</p> | <p class="principles">If no published instructions are available, specific instructions in writing from the manufacturer must be obtained and filed with RGC before project start-up.</p> | ||
Line 25: | Line 25: | ||
Membrane gussets must be installed to all inside and outside corners. | Membrane gussets must be installed to all inside and outside corners. | ||
− | {{strike| Modified Bituminous Base Sheet pre-stripping ply required at all perimeters, upstands and penetrations. Cap sheet stripping is required and must extend 150 mm (6") horizontally and 200 mm (8") vertically from the base of all upstands. All stripping terminating on vertical surfaces must be mechanically fastened. || 2019-July-8 }} | + | {{strike| Modified Bituminous Base Sheet pre-stripping ply required at all perimeters, upstands and penetrations. Cap sheet stripping is required and must extend 150 mm (6") horizontally and 200 mm (8") vertically from the base of all upstands. All stripping terminating on vertical surfaces must be mechanically fastened. || 2019-July-8 }} {{hilite | Replace with wording appropriate for single-ply stripping. || 2019-September-30 }} |
+ | |||
+ | ===Material Selection=== | ||
+ | |||
+ | TBA | ||
+ | |||
+ | ===Application=== | ||
==== Cant Strips and Edge Terminations ==== | ==== Cant Strips and Edge Terminations ==== | ||
− | Wood: Cant strips are only required as recommended by the membrane manufacturer. The use of hemlock lumber for construction of cant strips and related blocking is not acceptable. | + | |
+ | '''Wood''': Cant strips are only required as recommended by the membrane manufacturer. The use of hemlock lumber for construction of cant strips and related blocking is not acceptable. | ||
==== Expansion and Control Joints ==== | ==== Expansion and Control Joints ==== | ||
Line 46: | Line 53: | ||
==== Built-in Membrane Gutters ==== | ==== Built-in Membrane Gutters ==== | ||
<div class="principles">When a built in membrane gutter joins an RGC Guaranteed sloped roof; the gutter will be included by the Guarantee. Built-in membrane gutters that drain a roof not covered by an RGC Guarantee are not eligible for a Guarantee.</div> | <div class="principles">When a built in membrane gutter joins an RGC Guaranteed sloped roof; the gutter will be included by the Guarantee. Built-in membrane gutters that drain a roof not covered by an RGC Guarantee are not eligible for a Guarantee.</div> | ||
+ | |||
+ | |||
+ | Membranes installed as a gutter liner must be fully adhered and mechanically fastened at terminations. The accepted flexible membrane roofing system must be installed to RGC Guarantee Standards and the manufacturer’s printed instructions. | ||
+ | |||
+ | Built in gutter membranes must extend up the roof slope to a point, which is 150 mm (6") <b>vertically</b> above the maximum water level of the gutter or outside parapet height (see Section 7.5) “Built in Gutters for Water Shedding Roofing”). |
Revision as of 16:34, 30 June 2016
Contents
1 General
Membrane flashing (stripping) details (with the exception of low parapets, cant strip edges and RGC accepted door sill details) must be designed to provide a minimum 200 mm (8") sealed height above the finished roof surfacing. Surfacing is defined as the top of the roofing assembly, be it membrane, ballast or growing medium (soil). All membrane flashing (stripping) terminating on a vertical surface must be mechanically fastened.
Curbed openings (HVAC, skylights, etc.) must be a minimum height of 200 mm (8") and have at least one ply of membrane flashing (stripping) carried to the inside edge of the curb, or up under the built-in counter-flashing of pre-manufactured metal curbs (i.e. roof scuttles or HVAC) (see Detail Reference here).
Parapet walls may be less than 200 mm (8") in height, but not less than 87.7 mm (3½") in height.
All cant edge and parapet wall details must have membrane flashing (stripping) that overlaps the exterior finish (i.e. wall cladding) by a minimum of 50 mm (2"). On high parapet walls that are completely flashed with metal, where membrane flashing (stripping) is terminated part way up the wall, the remainder of the parapet must be covered with a flashing underlay of a minimum 40 mils or 1 mm (.040") self-adhered modified bitumen membrane. (see Detail Section reference needed).
All membrane flashing (stripping) terminating at cladded (i.e. stucco, siding, etc.) walls must lap under the sheathing membrane and cladding by minimum of 75 mm (3").
All membrane flashing (stripping) terminating under a reglet must be sealed to the wall with a compatible mastic (see Detail Section reference needed). Where a parapet, cant or separation / expansion joint detail intersects with a higher wall; the membrane flashing (stripping) must be sealed by gussets (membrane saddles) that are formed to protect the inside and outside corners (see Detail Section reference needed).
New construction projects must follow proper sequencing. Where roof flashings overlap work by others (i.e. siding, stucco, etc.), this work must be complete prior to the installation of metal flashing or wood blocking must be installed to facilitate the future installation of the exterior wall finish under the cap flashing. When lapping under work by others (siding, stucco, etc.), the membrane and metal roof flashings must be installed prior to any wall coverings. Any variance to proper detail sequencing must be approved by the design authority in writing (see Section reference needed).
Is this applicable to single-ply membranes?
If no published instructions are available, specific instructions in writing from the manufacturer must be obtained and filed with RGC before project start-up.
The roof system must be as per the complete tested assembly and a calculation for the building wind load requirements using the Wind-RCI calculator or Roofnav www.roofnav.comas applicable be submitted with project documents.
There is no minimum height requirement for exterior walls, (e.g. eave drip and gravel stop flashing).
Membrane gussets must be installed to all inside and outside corners.
Replace with wording appropriate for single-ply stripping.
2 Material Selection
TBA
3 Application
3.1 Cant Strips and Edge Terminations
Wood: Cant strips are only required as recommended by the membrane manufacturer. The use of hemlock lumber for construction of cant strips and related blocking is not acceptable.
3.2 Expansion and Control Joints
Roof Separation Joints (Expansion and Control Joints, etc.) / Equipment Sleepers / Safety Anchor Piers (poured in place pads) that are completely sealed (enveloped) with membrane flashing (stripping) may be less than 200 mm (8") in height but must not be less than 100 mm (4") in height above the finished roof surface.
Manufacturer’s proprietary roof expansion joint systems are acceptable for use when the systems are located a minimum of 200mm (8") above the finished roof surface and are completely sheathed (covered) with sloped metal flashing.
3.3 Door Openings
Door sill membrane flashing (stripping) may be less than 200 mm (8") in height but must not be less than 100 mm (4") above the primary roof membrane and must be installed to comply with the following conditions:
- A metal water stop flashing, formed with pan folded, welded or soldered corners must be mechanically attached to inside of door sill framing or opening and be sealed with membrane flashing (stripping).
- Membrane flashing, (stripping) or metal pan sill flashing must be installed at doorjamb framing or opening to a minimum height of 100 mm (4") above door sill framing or opening, prior to installation of doorjambs and door sills.
- Membrane gussets must be installed at sill corners.
- Metal pan sill flashings or RGC accepted reinforced liquid flashing systems must be installed wherever clearances preclude the use of membrane flashing (stripping) to seal door sill details.
- Slopes must be provided to direct water away from door sill details. (Overhangs are recommended wherever practical).
- Overflow drains in that area must be installed a minimum 25 mm (1") lower in height than adjacent door sills.
3.4 Built-in Membrane Gutters
Membranes installed as a gutter liner must be fully adhered and mechanically fastened at terminations. The accepted flexible membrane roofing system must be installed to RGC Guarantee Standards and the manufacturer’s printed instructions.
Built in gutter membranes must extend up the roof slope to a point, which is 150 mm (6") vertically above the maximum water level of the gutter or outside parapet height (see Section 7.5) “Built in Gutters for Water Shedding Roofing”).