Difference between revisions of "SBS 2-Part Retrofit Flashing (Cable Penetration)"

Jump to: navigation, search

Difference between revisions of "SBS 2-Part Retrofit Flashing (Cable Penetration)"

(RELATED WORK BY OTHERS)
Line 4: Line 4:
  
 
=== WORK INCLUDED ===
 
=== WORK INCLUDED ===
;(1) Gypsum Overlay Board:
+
;(1) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSSUBSTRATES|'''Gypsum Deck Overlay''']]: Required when insulation is too thin to span flutes of steel decking or as thermal barrier when specified by the design authority.
:Required when insulation is too thin to span flutes of steel decking or as thermal barrier when specified by the design authority. (See <i>RGC </i><i>Guarantee Standard A2.5</i>).
+
;(2) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSVAPOUR|'''Vapour Retarder''']]: If required by design authority.
;(2) Vapour Retarder:
+
;(3) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSINSULATION|'''Insulation''']]: Mechanically fastened where possible. See available insulation products in the [[Roof Deck Insulation|'''Accepted Materials''']] section of this Manual.
:If required by design authority.
+
;(4) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSINSULATIONOVERLAY|'''Insulation Overlay Board''']]: As required.
;(3) Insulation:
+
;(5) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSBASE|'''Base Sheet''']]: Adhered to overlay board using asphalt, cold adhesive, self-adhered, mechanical attachment or torch applied according to manufacturer's specification and to <i>RoofStar Guarantee Standards</i>. Torching directly to wood surfaces is not permitted.
:Mechanically fastened where possible. (See Section 2.2 for accepted materials and RGC Guarantee Standard A4.4).
+
;(6) '''Mastic''': Compatible with membrane
;(4) Insulation Overlay:
+
;(7) [[RoofStar Guarantee Standards for SBS Roof Systems#SBS-STRIPPING|'''Base Sheet Flashing''']]: Adhered according to manufacturer's specifications, using cold adhesive, self-adhered or torch applied. Must be carried up flashing and terminate under hood flange. Torching directly to wood surfaces is not permitted.
:As required. See <i>RGC Guarantee Standard C4.1</i>
+
;(8) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSBASE|'''Cap Sheet''']]: Applied according to manufacturer's printed instructions and to <i>RoofStar Guarantee Standards</i>.
;(5) Base Sheet:
+
;(9) [[RoofStar Guarantee Standards for SBS Roof Systems#SBS-STRIPPING|'''Cap Sheet Flashing''']]: Applied according to manufacturer's printed instructions and to <i>RoofStar Guarantee Standards</i>. Must be carried up flashing and terminate under hood flange.
:Adhered to overlay board using asphalt, cold adhesive, self-adhered, mechanical attachment or torch applied according to manufacturer&#8217;s specification and to <i>RGC Guarantee Standards</i>. Torching directly to wood surfaces is not permitted.
 
;(6) Mastic:
 
:Compatible with membrane
 
;(7) Base Sheet Flashing:
 
:Adhered according to manufacturer&#8217;s specifications, using cold adhesive, self-adhered or torch applied. Must be carried up flashing and terminate under hood flange. Torching directly to wood surfaces is not permitted. (See <i>RGC Guarantee Standards</i> Section 2.1.1, A5.6, and Section 2.1.3, C8.5).
 
;(8) Cap Sheet:
 
:Applied according to manufacturer&#8217;s printed instructions and to <i>RGC Guarantee Standards</i>.
 
;(9) Cap Sheet Flashing:
 
:Applied according to manufacturer&#8217;s printed instructions and to <i>RGC Guarantee Standards</i>. Must be carried up flashing and terminate under hood flange.
 
  
 +
<hr>
  
 
=== RELATED WORK BY OTHERS ===
 
=== RELATED WORK BY OTHERS ===
;(A) Acceptable Deck
+
;(A) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSDECKS|'''Acceptable Deck''']]
;(B) Wood Blocking
+
;(B) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSWOODBLOCKING|'''Wood Blocking''']]:
;(C) Two Piece Flashing:
+
;(C) [[RoofStar Guarantee Standards for SBS Roof Systems#SBSSTRIPFLASH|'''Two Piece Flashing''']]: Assembled around protrusion, laid in bed of compatible mastic on top of base sheet. Mechanically fasten two components together and fasten flange to wood blocking or deck.
:Assembled around protrusion, laid in bed of compatible mastic on top of base sheet. Mechanically fasten two componentstogether and fasten flange to wood blocking or deck.
 
  
  

Revision as of 18:52, 5 August 2016


D1.7.6.jpg


1 WORK INCLUDED

(1) Gypsum Deck Overlay
Required when insulation is too thin to span flutes of steel decking or as thermal barrier when specified by the design authority.
(2) Vapour Retarder
If required by design authority.
(3) Insulation
Mechanically fastened where possible. See available insulation products in the Accepted Materials section of this Manual.
(4) Insulation Overlay Board
As required.
(5) Base Sheet
Adhered to overlay board using asphalt, cold adhesive, self-adhered, mechanical attachment or torch applied according to manufacturer's specification and to RoofStar Guarantee Standards. Torching directly to wood surfaces is not permitted.
(6) Mastic
Compatible with membrane
(7) Base Sheet Flashing
Adhered according to manufacturer's specifications, using cold adhesive, self-adhered or torch applied. Must be carried up flashing and terminate under hood flange. Torching directly to wood surfaces is not permitted.
(8) Cap Sheet
Applied according to manufacturer's printed instructions and to RoofStar Guarantee Standards.
(9) Cap Sheet Flashing
Applied according to manufacturer's printed instructions and to RoofStar Guarantee Standards. Must be carried up flashing and terminate under hood flange.

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
(B) Wood Blocking
(C) Two Piece Flashing
Assembled around protrusion, laid in bed of compatible mastic on top of base sheet. Mechanically fasten two components together and fasten flange to wood blocking or deck.


NOTE: Refer to RGC Guarantee Standards for additional requirements.





Back to SBS Application

Back to SBS Construction Details

Back to Construction Details