=== WORK INCLUDED === | === WORK INCLUDED === | ||
− | + | ;(1) [[RoofStar Guarantee Standards for ASM Roof Systems#ASMUNDERLAYMENT|'''Underlayment''']]: The type of underlay required is determined by roof slope. | |
− | (1) | + | ;(2) [[RoofStar Guarantee Standards for ASM Roof Systems#ASMSLIP|'''Slip Sheet''']]: Recommended over asphaltic underlays and / or as required by metal roof panel manufacturer. |
− | + | ;(3) [[RoofStar Guarantee Standards for ASM Roof Systems#ASMVALLEYPAN |'''Valley Metal Panel''']]: Lower, installed prior to the pipe flashing, cut hole large enough to allow for movement. Extend 400 mm (16") upslope beyond the pipe. | |
− | (2) | + | ;(4) '''Flashing''': Flange set in two continuous beads of accepted caulking. |
− | + | ;(5) '''Spaced Cleat''': Cleats, set in accepted caulking, spaced 50 mm (2") and fastened with compatible non-corrosive flat head screws. | |
− | (3) | + | ;(6) '''Architectural Metal Roof Panel''': Upper, installed after installation of pipe flashing. Cut hole for pipe penetration and turn panel end under to accommodate cleats. |
− | + | ;(7) '''Settle Cap''': Material must match flashing material. | |
− | (4) | + | ;(8) '''Caulking''': Bead of caulking tooled into transition between metal roof panel and flashing. |
− | + | ;(9) '''Sealant Tape''': Two rows of sealant tape or acceptable caulking. | |
− | (5) | + | ;(10) [[RoofStar Guarantee Standards for ASM Roof Systems#ASMDRAG |'''Drag-load Fasteners''']]: Compatible non-corrosive fasteners. |
− | |||
− | (6) | ||
− | |||
− | (7) | ||
− | |||
− | (8) | ||
− | |||
− | (9) | ||
− | |||
− | (10) | ||
=== RELATED WORK BY OTHERS === | === RELATED WORK BY OTHERS === | ||
− | + | ;(A) [[RoofStar Guarantee Standards for ASM Roof Systems#ASMDECK|'''Acceptable Deck''']] | |
− | (A) | ||
− | '''NOTE''': Refer to | + | '''NOTE''': Refer to '''''RoofStar Guarantee Standards''''' for additional requirements. |
− | |||
<hr> | <hr> | ||
Line 38: | Line 26: | ||
+ | [[Section:E. Application: Steep Slope Roofs|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''ASM Application'']] | ||
− | + | [[Architectural Sheet Metal Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''ASM Construction Details'']] | |
− | |||
− | [[Architectural Sheet Metal Construction Details|<i class="fa fa-chevron-circle-left fa | ||
− | [[Section:G. Construction Details|<i class="fa fa-chevron-circle-left fa | + | [[Section:G. Construction Details|<i class="fa fa-chevron-circle-left fa" ></i> Back to ''Construction Details'']] |
Revision as of 17:54, 10 August 2016
1 WORK INCLUDED
- (1) Underlayment
- The type of underlay required is determined by roof slope.
- (2) Slip Sheet
- Recommended over asphaltic underlays and / or as required by metal roof panel manufacturer.
- (3) Valley Metal Panel
- Lower, installed prior to the pipe flashing, cut hole large enough to allow for movement. Extend 400 mm (16") upslope beyond the pipe.
- (4) Flashing
- Flange set in two continuous beads of accepted caulking.
- (5) Spaced Cleat
- Cleats, set in accepted caulking, spaced 50 mm (2") and fastened with compatible non-corrosive flat head screws.
- (6) Architectural Metal Roof Panel
- Upper, installed after installation of pipe flashing. Cut hole for pipe penetration and turn panel end under to accommodate cleats.
- (7) Settle Cap
- Material must match flashing material.
- (8) Caulking
- Bead of caulking tooled into transition between metal roof panel and flashing.
- (9) Sealant Tape
- Two rows of sealant tape or acceptable caulking.
- (10) Drag-load Fasteners
- Compatible non-corrosive fasteners.
2 RELATED WORK BY OTHERS
- (A) Acceptable Deck
NOTE: Refer to RoofStar Guarantee Standards for additional requirements.