SBS Conventionally Insulated System (alternate)

Jump to: navigation, search

SBS Conventionally Insulated System (alternate)

Revision as of 22:24, 30 October 2020 by James Klassen (talk | contribs) (WORK INCLUDED)
Notice to Reader
Images used in a Construction Detail are representative and not intended in their representation of an assembly to be prescriptive. Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the Standards, Guiding Principles and Recommendations of the RoofStar Guarantee Standards for a Waterproofing or Water-shedding System. Actual design with respect to dimensions, the selection of materials and their application remains the responsibility of the Design Authority.

The full text of applicable RoofStar Guarantee Standards may be read by using the blue hyperlinks
SBS Details

SBS 1.3.1-2 (Optional Hot Works).jpg


Click below for a printable version of this page (under development)
Print Sheet

1 WORK INCLUDED

(1) Supporting Deck Overlay
Optional, depending upon deck condition and roof system requirements.
(2) Air or Vapour Control Layer
Installed following the requirements of Part 6 in this Standard.
(3) Insulation
Installed in staggered and offset layers (not fully illustrated), and secured in accordance with the design of the system, which is based on the British Columbia Building Code, Part 4 and Part 5, and on Part 3 of the RoofStar Guarantee Standards for the membrane system type.
(4) Insulation Overlay
Subject to the requirements of Part 8 in the RoofStar Guarantee Standards for the membrane system type.
(5) Primer
As required by the membrane manufacturer.
(6) Base Membrane (pre-flashing, as illustrated)
Base membrane flashing is applied before the field membrane (pre-flashing), and is carried vertically up a wall or parapet at least 200 mm (8”); on parapets, carry the base membrane flashing over the outside face of the parapet at least 50 mm (2”) and secure it (see 10.3.5.1 (2)). Extend base membrane flashing onto the field substrate at least 100 mm (4”) (greater if required by the membrane manufacturer). See also Figure 10.2 (a through d) for sequential illustrations.
(7) Base Membrane (field)
Pre-flashing approach (Illustrated). Base field membrane is installed on a suitable, prepared substrate. See 9.3 for application requirements. If permitted by the membrane manufacturer, the field membrane may be turned up at the ends at least 100 mm (4”) (see illustration above), to protect any vulnerabilities at the change in plane. Also see 10.3.3 for other application approaches.
(8) Cap Membrane (field)
Granule-surfaced membrane, which may be adhered, self-adhered or heat-welded. See Tables 9.1 and 9.2 for acceptable cap membrane types and their securement options. See 9.3 for application requirements.
(9) Cap Membrane (flashing)
Extended vertically past the termination of the base membrane flashing, to provide a positive seal at the top edge. Membrane may be terminated at the top of the vertical plane or turned onto the top of the parapet as required by the manufacturer (9a).
(10) Metal Cap Flashing
Fabricated and secured according to the requirements in Part 13 METAL FLASHINGS.

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
(B) Suitable Wall Sheathing
If and as required.
(C) Sloped Parapet Top
Sloped to roof where parapet is over 100 mm (4") in width.
(D) Wall or Parapet Structure

NOTE: Refer to RoofStar Guarantee Standards for additional requirements.


Back to RoofStar Guarantee Standards for SBS Modified Bitumen Membrane Systems

Back to SBS Modified Bitumen Construction Details

Back to Construction Details