Draft CD 12

Jump to: navigation, search

Draft CD 12

Revision as of 16:09, 5 October 2020 by James Klassen (talk | contribs)
Notice to Reader
Images used in a Construction Detail are representative and not intended in their representation of an assembly to be prescriptive. Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the Standards, Guiding Principles and Recommendations of the RoofStar Guarantee Standards for a Waterproofing or Water-shedding System. Actual design with respect to dimensions, the selection of materials and their application remains the responsibility of the Design Authority.

The full text of applicable RoofStar Guarantee Standards may be read by using the blue hyperlinks
ASM Details

ASM 11.1.2 Pipe Flashing, Split Panel.jpg

Click below for a printable version of this page.
Print Sheet

1 WORK INCLUDED

(1) Underlayment
The type of underlay required is determined by roof slope.
(2) Insulation
Offset and stagger layers 300 mm (12").
(3) Separation layer
Vapour-permeable layer over insulation, required on all insulated Architectural Sheet Metal Roof Systems. The material must be located between the insulation and metal panels (see 8.1.2 Design).
(4) Ventilation layer
Recommended over asphaltic underlays and / or as required in this Standard (see 8.1.2 Design).


(1) Architectural Metal Roof Panel (lower)
Lower, installed prior to the pipe flashing, cut hole large enough to allow for movement. Extend 400 mm (16") upslope beyond the pipe.
(2) Settlement Cap
Material must match flashing material.
(3) Drag-load Fasteners
Compatible non-corrosive fasteners.
(4) Sealant Tape
Two rows of sealant tape or acceptable caulking.
(5) Caulking
Bead of caulking tooled into transition between metal roof panel and flashing.
(6) Protrusion Flashing
Flange set in two continuous beads of accepted caulking.
(7) Metal Clip on Bearing Plate.
(8) Separation Layer (Drainage Mat)
Required for slopes less than 1:3; recommended over asphaltic underlays and / or as required by metal roof panel manufacturer.
(9) Underlayment
The type of underlay required is determined by roof slope.
(10) Spaced Cleat
Cleats, set in accepted caulking, spaced 50 mm (2") and fastened with compatible non-corrosive flat head screws.
(11) Architectural Metal Roof Panel (upper)
Upper, installed after installation of pipe flashing. Cut hole for pipe penetration and turn panel end under to accommodate cleats.

2 RELATED WORK BY OTHERS

(A) Acceptable deck
(B) Wall control layers
must be positively lapped with roof materials and flashings, to maintain continuity across systems.
(C) Wall cladding

NOTE: Refer to RoofStar Guarantee Standards for additional requirements.


RoofStar Guarantee Standards for Architectural Sheet Metal (ASM) Systems

Back to ASM Construction Details