Draft CD 8

Jump to: navigation, search

Draft CD 8

Revision as of 21:26, 11 February 2020 by James Klassen (talk | contribs)
Notice to Reader
Images used in a Construction Detail are representative and not intended in their representation of an assembly to be prescriptive. Nor are they necessarily drawn to scale. Rather, they are provided to visually convey the Standards, Guiding Principles and Recommendations of the RoofStar Guarantee Standards for a Waterproofing or Water-shedding System. Actual design with respect to dimensions, the selection of materials and their application remains the responsibility of the Design Authority.

RoofStar Guarantee Standards are blue-linked
SBS Details

SBS 11.3.3.2-1 Basic Curb.jpg


Click below for a printable version of this page.
Print Sheet


1 WORK INCLUDED

(1) Supporting Deck Overlay
Optional, depending upon deck condition and roof system requirements.
(2) Air or Vapour Control Layer
Installed following the requirements of Part 6 in this Standard. Tie field layers into curb, ensuring continuity.
(3) Insulation
Installed in staggered and offset layers (not illustrated), and secured in accordance with the design of the system, which is based on the British Columbia Building Code, Part 4 and Part 5, and on Part 3 of the RoofStar Guarantee Standards for the membrane system type.
(4) Insulation Overlay
Subject to the requirements of Part 8 in the RoofStar Guarantee Standards for the membrane system type.
(5) Primer for Base Membrane Flashing
As required by the membrane manufacturer.
(6) Base Membrane (field)
Mechanically attached, torch-applied, adhered or self-adhered. See Tables 9.1 and 9.2 for acceptable membrane types and securement options. See 9.3 for application requirements.
(7) Base Membrane (flashing)
Carried vertically up a wall or parapet at least 200 mm (8”), and onto the roof field at least 100 mm (4”) (greater if required by the membrane manufacturer).
(7) Cap Membrane (field)
Granule-surfaced membrane. See Tables 9.1 and 9.2 for acceptable cap membrane types and their securement options. See 9.3 for application requirements.
(8) Cap Membrane (flashing)
Extended vertically past the termination of the base membrane flashing, to provide a positive seal at the top edge.
(9) Metal Counter-flashing
Secure metal flashings with appropriate fasteners set at least 87 mm (3 ½”) above the finished roof surface.

2 RELATED WORK BY OTHERS

(A) Acceptable Supporting Deck Structure
(B) Air and Vapour Control Layer Seal
(C) Wood Blocking
Minimum 200 mm (8") in height. (See asphalt adhered or mechanically fastened. Two layers required over heat-sensitive insulation. Cant is optional).

NOTE: Refer to RoofStar Guarantee Standards for additional requirements.




Back to RoofStar Guarantee Standards for SBS Modified Bitumen Membrane Systems

Back to SBS Modified Bitumen Construction Details

Back to Construction Details