TS Details:E4.7.4 (Tile - Roof/Wall Transition)

Jump to: navigation, search

TS Details:E4.7.4 (Tile - Roof/Wall Transition)

Revision as of 16:56, 23 December 2015 by James Klassen (talk | contribs) (Created page with "<hr> Flashings bridge the gap between field areas and any protrusions such as pipes, vents, and adjoining walls. Because these items impede the flow of water, small deficienci...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

Flashings bridge the gap between field areas and any protrusions such as pipes, vents, and adjoining walls. Because these items impede the flow of water, small deficiencies can cause high amounts of water to enter the building. Proper detail work will make the difference between a successful or problematic roof.Flashing for a wall termination should lap the tile by a minimum of 100 mm (4"). Material should be the 26 ga. prepainted galvanized with S locks or standing seams to join lengths.

7.3.2.2.16.jpg

A mortar or mastic bedding should be applied to the tops of the concrete tile before flashing to prevent wind blown rain or vermin from entering.



Back to Slate Application

Back to Tile and Slate Construction Details

Back to Construction Details