WP Details:F1.7.6 (Walls - Planter Pre-Curb Wall)

Jump to: navigation, search

WP Details:F1.7.6 (Walls - Planter Pre-Curb Wall)

Revision as of 17:53, 23 December 2015 by James Klassen (talk | contribs) (RELATED WORK BY OTHERS)

D1.7.8.jpg

D1.7.8a.jpg


1 WORK INCLUDED

(1) Primary Waterproofing Membrane: Fully adhered to acceptable substrates (concrete slab depicted), installed as per RGC Guarantee Standards E and Membrane Manufacturer's installation specifications.

(2) Membrane Primer or Adhesive: proprietary primer or adhesive, application and quantities as directed by membrane manufacturers published application specifications.

(3) Pre-Curb (Start-Up Curb) Membrane Flashing: Two ply of membrane flashing (elastomeric, plastomeric, or modified bituminous) completely enclosing pre-curb and installed as per membrane manufacturer's published application specifications. Install membrane reinforcement gussets at all corner detail transitions.

(4) Proprietary liquid membrane flashing System: RGC accepted Liquid Membrane Flashing System(s) (Refer to RPM Section2.2 for accepted systms. Install as per Manufacturer's published instructions.

(5) Inside Planter Wall Membrane Flashing: Adhered according to manufacturer's specifications. Carry membrane flashing plies to reglet termination near top of planter wall (stagger membrane seal minimum 300mm (6").

(6) Reglet Metal Counter Flashing: As required by RGC Guarantee Standards E. (7) Plaza Deck Assembly: Extruded polystyrene insulation and filter mat (optional) over primary waterproofing membrane. Concrete pavers placed above pre-curb membrane flashing height on proprietary pedestals. Note: membrane and metal wall counter flashing is not required above pre-curb membrane flashing on plaza deck side of planter walls.


2 RELATED WORK BY OTHERS

(A) Acceptable Deck: Concrete slab shown

(B) Pre- Curb: Minimum of 100mm (4") in height above concrete deck, smooth dry and clean.

(C) Cast over Concrete Planter Wall: Form on top of membrane sealed Pre-curbs or Start-up curbs.

(D) Re-Bar: Placed at centre of Pre-curb.

(E) Reglet: Premanufactured purpose-made reglet cast in concrete wall or saw-cut.

(F) Alternate Termination: Horizontal Reglet alternative to premanufactured purpose-made reglet cast in concrete wall or saw-cut on vertical surface of inside planter walls.

NOTE: Refer to RGC Guarantee Standards E for additional requirements.