SBS Metal Edge Termination
Revision as of 18:53, 27 June 2022 by James Klassen (talk | contribs)
Division D - Construction Details
SBS | Metal Edge Termination ( Article 10.3.4.2.)
Notice to Reader | |
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).
The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text. |
SBS Details
1 WORK INCLUDED
- (1) Primer
- For self-adhered or torch-applied base membranes, as required by the membrane manufacturer.
- (2) Base Membrane (field)
- Torch-applied, adhered, self-adhered (as illustrated), or mechanically attached (subject to deck type and wind uplift design requirements). See Tables 9.1 and 9.2 for acceptable membrane types and securement options. See 9.3 for application requirements.
- (3) Mastic
- Applied beneath metal edge flashing. Refer to 10.3.5.2 (3)(2).
- (4) Metal Edge Flashing
- See 13.3.2 Fabrication for manufacturing requirements. See also 10.3.1.4 Low Roof Edges for application standards and securement. Hemmed edges are required; a kicked-out drip edge is optional but recommended (cf. 13.1.2.2 (10)).
- (5) Base Membrane (flashing)
- Applied to overlap metal flashing and the field base membrane.
- (6) Cap Membrane (field)
- Installed according to Part 9 standards and sealed along the exposed edge with an un-tooled bead of membrane compatible sealant (cf. 10.3.5.2 (3)(7)(2)).
2 RELATED WORK BY OTHERS
- (A) Acceptable Substrate
- Representative
- (B) Wall Assembly
- Representative
NOTE: See the Standard for additional requirements.