Asphalt Shingles - Intersection with Waterproofing Roof (Lower)
Asphalt Shingles - Intersection with Waterproofing Roof (Lower)
Revision as of 14:11, 5 October 2022 by James Klassen (talk | contribs)
Division D - Construction Details
Asphalt Shingles | Intersection with Waterproofing Roof (Lower) ( Article 10.3.7.2.)
Notice to Reader | |
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).
The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text. |
Asphalt Shingle Details
1 WORK INCLUDED
- (1) Underlayment
- Required, and installed to overlap the Valley Protection Membrane and the Valley Metal Flashing. Install ‘shingle-style’, following the requirements for side and end laps; use acceptable fasteners, or adhere (if a self-adhering membrane) in keeping with the manufacturer’s published requirements.
- (2) Starter Shingles
- (3) Field Shingles
- Fasteners used to secure shingles must be at least 300 mm (12") above the finished surface of the roof waterproofing system.
- (4) Waterproofing roof system
- Secure membrane to water-shedding roof deck at least 300 mm (12") above the finished surface of the roof waterproofing (refer to the related Membrane Standards, Part 9 FIELD MEMBRANE and Part 10 PERIMETERS and WALLS).
2 RELATED WORK BY OTHERS
- (A) Acceptable Deck
NOTE: See the Standard for additional requirements.