SBS Flanged Insert Drain
SBS Flanged Insert Drain
Division D - Construction Details
SBS | Flanged Insert Drain ( Article 11.3.3.6.)
Notice to Reader | |
Images used in a Construction Detail are representative and not prescriptive, and are not necessarily drawn to scale. They are intended to support the related Standard (Ref. Division A, Article 2.2.1.2.).
The reader may link to the related Article in the detail title, or link to the Standard as it relates to a specific element in the detail. All hyperlinks are displayed blue text. |
SBS Details
1 WORK INCLUDED
- (1) Supporting Deck Overlay
- If required by design authority.
- (2) Air or Vapour Control Layers
- If required by design authority.
- (3) Insulation
- See available insulation products in the Accepted Materials Division of this Manual.
- (4) Insulation Overlay
- Where required.
- (5) Primary Membrane and Membrane Protection
- (6) Mastic
- As approved by manufacturer.
- (7) Roof Drain Membrane Flashing
- Onto primed drain flange or adhesive for non-bituminous flexible membrane systems. See also Article 11.3.3.6.
2 RELATED WORK BY OTHERS
- Leader size is determined by using the calculation found in the BC Building Code at Appendix P.7.4.10 and Section 7.4.10.11 (Section 7.4.10.10 for gutters) in conjunction with the 15-minute rainfall value from the National Building Code, Appendix C.
NOTE: See the Standard for additional requirements.