SBS Parapet-Wall Connection

Jump to: navigation, search

SBS Parapet-Wall Connection

Revision as of 15:36, 19 July 2016 by James Klassen (talk | contribs) (Created page with "File:10.3.1.4.jpg === WORK INCLUDED === (1) <b>Gypsum Overlay Board: </b>If required by design authority. (2) <b>Vapour Retarder</b>: If required by design authority....")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

10.3.1.4.jpg

1 WORK INCLUDED

(1) Gypsum Overlay Board: If required by design authority.

(2) Vapour Retarder: If required by design authority.

(3) Insulation: See list of accepted materials in Section 2.2.

(4) Insulation Overlay: As required. See RGC Guarantee Standard B4.1, B4.2 and C4.1

(5) Primary Membrane and Membrane Protection

(6) Membrane Flashing: Mechanically fasten at terminations. At least one ply must extend over outside edge. See RGC Guarantee Standard A5.6

(7) Metal Base Flashing: Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats. See RGC Guarantee Standard A6.9

(8) Metal Cap Flashing: Must overlap exterior wall finish. See RGC Guarantee Standard A6.9 Fasten with concealed clip-type fasteners or cladding screws evenly spaced between seams. See RGC Guarantee Standard A6.10.

(9) Wall Tie-In Membrane: Minimum 2 mm (0.078") self-adhered modified bitumen or flexible membrane manufacturer’s approved detail.

(10) Metal Counter Flashing

2 RELATED WORK BY OTHERS

(A) Acceptable Deck

(B) Air / Vapour Seal

(C) Acceptable Wall Surface

(D) Wood Blocking

(E) Sloped Wood Blocking: Required over 100 mm (4") parapet width. See RGC Guarantee Standard A6.9

(F) Wall Sheathing Membrane

(G) Wall Cladding

NOTE: Refer to RGC Guarantee Standards for additional requirements.





Back to SBS Application

Back to SBS Construction Details

Back to Construction Details