1 WORK INCLUDED

(1) Gypsum Overlay Board: If required by design authority.

(2) Vapour Retarder: If required by design authority.

(3) Insulation: See list of accepted materials in Section 2.2.

(4) Insulation Overlay: Where required. See RGC Guarantee Standard B4.1, B4.2 and C4.1

(5) Primary Membrane and Membrane Protection

(6) Mastic: As approved by manufacturer.

(7) Membrane Flashing: Onto primed drain flange or adhesive for non-bituminous flexible membrane systems.

2 RELATED WORK BY OTHERS =

(A) Acceptable Deck

(B) Roof Drain Assembly

NOTE
  • Refer to RGC Guarantee Standards for additional requirements
  • Leader size is determined by using the calculation found in the BC Building Code at Appendix P.7.4.10 and Section 7.4.10.11 (Section 7.4.10.10 for gutters) in conjunction with the 15-minute rainfall value from the National Building Code, Appendix C.
Refer to RGC Guarantee Standards for additional requirements.