ASM 10.4.3 Ridge (Vented)
ASM 10.4.3 Ridge (Vented)
1 WORK INCLUDED
(1) Underlayment: The type of underlay required is determined by roof slope (see Section 8.1.4.1 and Section 8.1.4.2).
(2) Slip Sheet: Recommended over asphaltic underlays and / or as required by metal roof panel manufacturer.
(3) Architectural Metal Roof Panel: Turn up (bread panned) at termination and drag load fastened with compatible non-corrosive fasteners.
(4) Metal Panel Clip: Installed to metal roof panel manufacturer’s printed instructions.
(5) ‘Z’ Closure: Set in accepted caulking and secured with compatible non-corrosive flat head fasteners.
(6) Perforated Metal Screen
(7) Continuous Cleat
(8) Metal Cap Flashing: Joints overlapped 100 mm (4") minimum, sealed with two rows of accepted caulking. Exposed edges must be turned under.
2 RELATED WORK BY OTHERS
(A) Acceptable Deck
(B) Wood Nailer
(C) Air Space: Determined by Design Authority.
NOTE: Refer to RGC Guarantee Standards for additional requirements.