SBS Fire Separation Joint
SBS Fire Separation Joint
Revision as of 18:16, 4 August 2016 by James Klassen (talk | contribs)
1 WORK INCLUDED
- (1) Gypsum Deck Overlay
- If required by design authority.
- (2) Vapour Retarder
- If required by design authority.
- (3) Insulation
- See available insulation products in the Accepted Materials section of this Manual.
- (4) Insulation Overlay Board
- Where required.
- (5) Primary Membrane and Membrane Protection
- (6) MembraneFlashing
- >
- (7) Membrane Counter Flashing
- (8) Base Metal Flashing
- Mechanically fasten to top of plywood backing. Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
- (9) Metal Flashing / Cladding
- (10) Secondary Metal Cap Flashing
- Joints to be offset from Cap Flashing, OR Water Channeling Clip may be used (See Inset, Section 10.3), OR solder standing seam joints. Do NOT place combustible materials over top of firewall.
- (11) Metal Cap Flashing
- Standing seam joints required.
2 RELATED WORK BY OTHERS
- (A) Acceptable Deck
- (B) Acceptable Wall Surface (Plywood)
- (C) Wood Blocking
- (D) Grouted Finish
- Sloped surface to promote drainage off cap flashing.
NOTE: Refer to RGC Guarantee Standards for additional requirements.