SBS Parapet-Wall Connection

Jump to: navigation, search

SBS Parapet-Wall Connection

Revision as of 20:52, 5 August 2016 by James Klassen (talk | contribs) (RELATED WORK BY OTHERS)

10.3.1.4.jpg

1 WORK INCLUDED

(1) Gypsum Deck Overlay
If required by design authority.
(2) Vapour Retarder
If required by design authority.
(3) Insulation
See list of Accepted Materials.
(4) Insulation Overlay Board
As required.
(5) Primary Membrane and Membrane Protection
(6) Membrane Flashing (attachment & termination)
Mechanically fasten at terminations. At least one ply must extend over outside edge.
(7) Metal Base Flashing
Optional on flexible membrane systems. Required on assemblies using gravel ballast filter mats.
(8) Metal Cap Flashing
Must overlap exterior wall finish. Fasten with concealed clip-type fasteners or cladding screws evenly spaced between seams.
(9) Wall Tie-in
Minimum 2 mm (0.078") self-adhered modified bitumen or flexible membrane manufacturers approved detail.
(10) Metal Counter-flashing

2 RELATED WORK BY OTHERS

(A) Acceptable Deck
(B) Air/Vapour Seal
(C) Acceptable Wall Surface
(D) Wood Blocking
(E) Sloped Wood Blocking
Required over 100 mm (4") parapet width.
(F) Wall Sheathing Membrane
Minimum 1 mm (0.040") self-adhered modified bitumen.
(G) Wall Cladding


NOTE: Refer to RoofStar Guarantee Standards for additional requirements.